The Hornsea Two Offshore Wind Farm Order 2016

Port traffic management planE+W+S

16.—(1) No part of the authorised development seaward of MLWS (excluding ducting and related works which are an integral part of works landward of MLWS) may be commenced until—

(a)a traffic management plan for the onshore port-related traffic to and from the selected base port or ports for construction or operation (or both) of that part of the authorised development has been submitted to and approved by the relevant planning authority in consultation with the relevant highway authority; or

(b)the relevant planning authority has confirmed, after consultation with the relevant highway authority, that no traffic management plan is required for that part of the authorised development.

(2) All traffic management plans must be implemented as approved at all times specified within the relevant traffic management plan during the construction and operation of the authorised development.

(3) In this Requirement—

“relevant highway authority” means the highway authority in whose area the selected base port is located;

“relevant planning authority” means the local planning authority in whose area the selected base port is located;

“selected base port” means a port situated in England and/or Wales and used by management personnel for the construction or ongoing operational management of the authorised development (or both).