Post-acceptance scheduling and completion of works: single LV service demand connections and small project demand connections

8.—(1) This regulation applies to an electricity distributor where it receives—

(a)a customer’s written acceptance of a quotation relating to a single LV service demand connection or a small project demand connection within the requisite timescale specified by the electricity distributor in that quotation;

(b)payment of any amount due to be paid to the electricity distributor in accordance with the accepted quotation—

(i)in respect of paragraph (2), on acceptance of the quotation; or

(ii)in respect of paragraph (3), prior to completion of the works or a phase of the works (as applicable);

(c)any reasonable security required by the electricity distributor under section 20(1) of the Act(1);

(d)written acceptance of any additional terms of connection proposed by the electricity distributor under section 21 of the Act(2); and

(e)details of any reasonable means by which the customer may be contacted in Great Britain by the electricity distributor during the period 9am to 5pm on a working day in respect of the quotation.

(2) Where this regulation applies and the electricity distributor fails within the prescribed period from the applicable date to contact the customer to commence the process of agreeing a schedule of dates for completion of the works specified in the accepted quotation, the electricity distributor must, except in any of the circumstances described in regulation 15, pay to the customer the prescribed sum.

(3) Where this regulation applies and a relevant date has been agreed between the electricity distributor and the customer, if the electricity distributor fails to complete the works (or a phase of the works) provided for in the accepted quotation by the agreed date, the electricity distributor must, except in any of the circumstances described in regulations 15(2), 15(3), 15(7), 15(8) and 16, pay to the customer the prescribed sum.

(1)

1989 c.29; section 20 was amended by section 47 of, and schedule 8 to, the Utilities Act 2000 (c.27) and modified by sectin 3(2) of that Act.

(2)

1989 c.29; section 21 was amended by section 47 of, and Schedule 8 to, the Utilities Act 2000 (c.27) and modified by section 3(2) of that Act.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources