The Town and Country Planning (General Permitted Development) (England) Order 2015

Conditions
This section has no associated Explanatory Memorandum

M.2  Development is permitted by Class M subject to the following conditions—

(a)it is carried out in accordance with the details given in the notice sent to the mineral planning authority referred to in paragraph M.1(a), unless that authority have agreed otherwise in writing;

(b)if the mineral planning authority so require, the developer must within a period of 3 months from the date of the requirement (or such other longer period as that authority may provide) submit to them for approval a scheme providing for the restoration and aftercare of the site;

(c)where such a scheme is required, the site is restored and aftercare is carried out in accordance with the provisions of the approved scheme; and

(d)development is not be commenced until the relevant period has elapsed.