SCHEDULE 2Permitted development rights

PART 17Mining and mineral exploration

Class C – developments for maintenance or safety

Permitted development

C.  The carrying out of development required for the maintenance or safety of a mine or a disused mine or for the purposes of ensuring the safety of the surface of the land at or adjacent to a mine or a disused mine.

Development not permitted

C.1  Development is not permitted by Class C if it is carried out by the Coal Authority or any licensed operator within the meaning of section 65 of the Coal Industry Act 1994 (interpretation)(1).

Conditions

C.2—(1) Subject to sub-paragraphs (2) and (3), development is permitted by Class C subject to the prior approval of the mineral planning authority(2) of detailed proposals for the siting, design and external appearance of the building, plant or machinery proposed to be erected, installed, extended or altered.

(2) The prior approval referred to in sub-paragraph (1) is not required if—

(a)the external appearance of the mine or disused mine at or adjacent to which the development is to be carried out would not be materially affected;

(b)no building, plant, machinery, structure or erection—

(i)would exceed a height of 15 metres above ground level, or

(ii)where any building, plant, machinery, structure or erection is rearranged, replaced or repaired, would exceed a height of 15 metres above ground level or the height of what was rearranged, replaced or repaired, whichever is the greater, and

(c)the development consists of the extension, alteration or replacement of an existing building, within the limits set out in sub-paragraph (4).

(3) The prior approval referred to in sub-paragraph (1) may not be refused or granted subject to conditions unless the authority are satisfied that it is expedient to do so because—

(a)the proposed development would injure the amenity of the neighbourhood and modifications could reasonably be made or conditions reasonably imposed in order to avoid or reduce that injury; or

(b)the proposed development ought to be, and could reasonably be, sited elsewhere.

(4) The limits referred to in paragraph C.2(2)(c) are—

(a)that the cubic content of the building as extended, altered or replaced does not exceed that of the existing building by more than 25%; and

(b)that the floor space of the building as extended, altered or replaced does not exceed that of the existing building by more than 1,000 square metres.

(1)

1994 c. 32; which was amended by S.I. 2009/1941. See also section 25 concerning coal-mining operations to be licensed.

(2)

See section 1(4) of the Act.