SCHEDULE 2Permitted development rights

PART 15Power related development

Class A – gas transporters

Conditions

A.2  Development is permitted by Class A subject to the following conditions—

(a)in the case of any Class A(a) development, not less than 8 weeks before the beginning of operations to lay a notifiable pipe-line, the gas transporter must give notice in writing to the local planning authority of its intention to carry out that development, identifying the land under which the pipe-line is to be laid;

(b)in the case of any Class A(d) development, on completion of the laying or construction of the main or pipe, or at the expiry of a period of 9 months from the beginning of the development, whichever is the sooner, any pipes or other apparatus still stored on the land are removed and the land restored as soon as reasonably practicable to its condition before the development took place (or to any other condition which may be agreed with the local planning authority); and

(c)in the case of any Class A(e) development, approval of the details of the design and external appearance of the building must be obtained, before the development is begun, from—

(i)in Greater London or a metropolitan county, the local planning authority,

(ii)in a National Park, outside a metropolitan county, the county planning authority,

(iii)in any other case, the district planning authority(1).

(1)

See section 1(1) of the Act, which was amended by section 31 of the Greater London Authority Act 2007 (c. 24); there are other amendments not relevant to this Order.