SCHEDULE 2Permitted development rights

PART 14Renewable energy

Class I – installation or alteration etc of stand-alone wind turbine on domestic premises

Development not permitted

I.2  Development is not permitted by Class I if—

(a)in the case of the installation of a stand-alone wind turbine, the development would result in the presence of more than 1 stand-alone wind turbine within the curtilage of the dwellinghouse or block of flats;

(b)in the case of the installation of a stand-alone wind turbine, a wind turbine is installed on the dwellinghouse or on a building within the curtilage of the dwellinghouse or the block of flats;

(c)in the case of the installation of a stand-alone wind turbine, an air source heat pump is installed on the dwellinghouse or block of flats or within the curtilage of the dwellinghouse or block of flats;

(d)the highest part of the stand-alone wind turbine would exceed 11.1 metres in height;

(e)the distance between ground level and the lowest part of any blade of the stand-alone wind turbine would be less than 5 metres;

(f)any part of the stand-alone wind turbine (including blades) would be located in a position which is less than a distance equivalent to the overall height (including blades) of the stand-alone wind turbine plus 10% of its height when measured from any point along the boundary of the curtilage;

(g)the swept area of any blade of the stand-alone wind turbine exceeds 3.8 square metres;

(h)the stand-alone wind turbine would be installed on safeguarded land;

(i)the stand-alone wind turbine would be installed on a site designated as a scheduled monument;

(j)the stand-alone wind turbine would be installed within the curtilage of a building which is a listed building;

(k)in the case of land within a conservation area, the stand-alone wind turbine would be installed so that it is nearer to any highway which bounds the curtilage than the part of the dwellinghouse or block of flats which is nearest to that highway; or

(l)the stand-alone wind turbine would be installed on article 2(3) land other than land within a conservation area.