The Construction (Design and Management) Regulations 2015

Regulation 6

SCHEDULE 1Particulars to be notified under regulation 6

This schedule has no associated Explanatory Memorandum

1.  The date of forwarding the notice.

2.  The address of the construction site or precise description of its location.

3.  The name of the local authority where the construction site is located.

4.  A brief description of the project and the construction work that it entails.

5.  The following contact details of the client: name, address, telephone number and (if available) an email address.

6.  The following contact details of the principal designer: name, address, telephone number and (if available) an email address.

7.  The following contact details of the principal contractor: name, address, telephone number and (if available) an email address.

8.  The date planned for the start of the construction phase.

9.  The time allocated by the client under regulation 4(1) for the construction work.

10.  The planned duration of the construction phase.

11.  The estimated maximum number of people at work on the construction site.

12.  The planned number of contractors on the construction site.

13.  The name and address of any contractor already appointed.

14.  The name and address of any designer already appointed.

15.  A declaration signed by or on behalf of the client that the client is aware of the client duties under these Regulations.