The Construction (Design and Management) Regulations 2015

Appointment of the principal designer and the principal contractor

This section has no associated Explanatory Memorandum

5.—(1) Where there is more than one contractor, or if it is reasonably foreseeable that more than one contractor will be working on a project at any time, the client must appoint in writing—

(a)a designer with control over the pre-construction phase as principal designer; and

(b)a contractor as principal contractor.

(2) The appointments must be made as soon as is practicable, and, in any event, before the construction phase begins.

(3) If the client fails to appoint a principal designer, the client must fulfil the duties of the principal designer in regulation 11 and 12.

(4) If the client fails to appoint a principal contractor, the client must fulfil the duties of the principal contractor in regulations 12 to 14.