19.Statutory authority to override easements and other rights
20.Time limit for exercise of authority to acquire land compulsorily
23.Application of the Compulsory Purchase (Vesting Declarations) Act 1981
27.Temporary use of land for carrying out the authorised development
28.Temporary use of land for maintaining the authorised development
30.Apparatus and rights of statutory undertakers in streets subject to temporary prohibition or restriction
STREETS SUBJECT TO PERMANENT AND TEMPORARY ALTERATION OF LAYOUT
MODIFICATION OF COMPENSATION AND COMPULSORY PURCHASE ENACTMENTS FOR CREATION OF NEW RIGHTS
3.(1) The 1965 Act has effect with the modifications necessary...
4.For section 7 of the 1965 Act (measure of compensation)...
6.The following provisions of the 1965 Act (which state the...
8.Section 20 of the 1965 Act (protection for interests of...
9.Section 22 of the 1965 Act (protection of acquiring authority’s...
PART 1 FOR THE PROTECTION OF NATIONAL GRID
3.Except for paragraphs 4 (apparatus in streets subject to temporary...
4.Apparatus of National Grid in streets subject to temporary prohibition or restriction
8.Retained apparatus: protection of National Grid as Gas Undertaker
9.Retained apparatus: protection of National Grid as Electricity Undertaker
PART 2 FOR THE PROTECTION OF ELECTRICITY, GAS, WATER AND SEWERAGE UNDERTAKERS
16.For the protection of the utility undertakers referred to in...
17.In this Part of this Schedule— “alternative apparatus” means alternative...
18.This Part of this Schedule does not apply to apparatus...
19.Regardless of the temporary prohibition or restriction of use of...
20.Regardless of any provision in this Order or anything shown...
22.(1) Where, in accordance with the provisions of this Part...
23.(1) Not less than 28 days before starting the execution...
24.(1) Subject to the following provisions of this paragraph, the...
25.(1) Subject to sub-paragraphs (2) and (3), if by reason...
26.Nothing in this Part of this Schedule affects the provisions...
PART 3 FOR THE PROTECTION OF OPERATORS OF ELECTRONIC COMMUNICATIONS CODE NETWORKS
PART 4 FOR THE PROTECTION OF EASTERN POWER NETWORKS
32.For the protection of Eastern Power Networks as referred to...
33.In this Part of this Schedule— “alternative apparatus” means alternative...
34.This Part of this Schedule does not apply to apparatus...
35.Regardless of the temporary prohibition or restriction of use of...
36.Regardless of any provision in this Order or anything shown...
38.(1) Where, in accordance with the provisions of this Part...
39.(1) Not less than 28 days before starting the execution...
40.(1) Subject to the following provisions of this paragraph, the...
41.(1) Subject to sub-paragraphs (2) and (3), if by reason...
42.Nothing in this Part of this Schedule affects the provisions...