SCHEDULE 1Authorised development, ancillary and necessary works and Requirements
PART 3Requirements
Honeycomb worm translocation strategy30
1
No part of the authorised development shall be commenced until a written strategy for the translocation of the honeycomb worm (Sabellaria alveolata) has been submitted to and approved by the relevant planning authority in consultation with Natural Resources Wales.
2
The honeycomb worm translocation strategy is to provide for—
a
a method statement for the translocation effort;
b
identification of temporary or permanent receptor sites;
c
translocation of casts to encourage future settlement to locations around the new seawalls;
d
provision of rockpools and features similar to bio-blocks to provide biodiversity offset; and
e
further remedial action to be implemented in the event of an unsuccessful translocation programme or a detrimental effect upon the adjacent undisturbed honeycomb worm reef.
3
The approved honeycomb worm translocation strategy and any measures under it are to be implemented and maintained during construction and operation of the authorised development.