The White Moss Landfill Order 2015

Restoration and aftercare

7.—(1) Following certification in writing by the county planning authority of the completion of restoration in any phase on the application land, aftercare of that phase must be carried out for a period of 20 years in accordance with the landscaping, restoration, habitat management and aftercare scheme listed in requirement 4(11).

(2) By the end of October in each year until the end of the aftercare period in the final phase on the application land, a report must be submitted to the county planning authority recording in detail:

(a)The operations carried out on the land during the previous 12 months in respect of landfilling;

(b)The measures taken to implement the restoration and aftercare provisions;

(c)The intended operations for the next 12 months which will be implemented on the application land; and

(d)The report must contain the topographical survey specified under requirement 24 to this Order.