Regulation 36
SCHEDULE 6Expenditure for individual technologies
This schedule has no associated Explanatory Memorandum
PART 1Biomass plants
Table 1
Assessment date | Expenditure threshold | Growth threshold | Super expenditure threshold | Super growth threshold |
---|
31st July 2014 | £ 2.40m | - | £ 4.80m | - |
31st October 2014 | £ 4.20m | £ 1.80m | £ 8.40m | £ 3.60m |
31st January 2015 | £ 6.00m | £ 1.80m | £ 12.00m | £ 3.60m |
30th April 2015 | £ 8.40m | £ 2.40m | £ 16.80m | £ 4.80m |
31st July 2015 | £ 11.90m | £ 3.60m | £ 23.90m | £ 7.20m |
31st October 2015 | £ 15.50m | £ 3.60m | £ 31.10m | £ 7.20m |
Any date after 30th January 2016 | £ 19.10m | £ 3.60m | £ 38.20m | £ 7.20m |
PART 2Air source heat pumps
Table 2
Assessment date | Expenditure threshold | Growth threshold | Super expenditure threshold | Super growth threshold |
---|
31st July 2014 | £ 2.40m | - | £ 4.80m | - |
31st October 2014 | £ 4.20m | £ 1.80m | £ 8.40m | £ 3.60m |
31st January 2015 | £ 6.00m | £ 1.80m | £ 12.00m | £ 3.60m |
30th April 2015 | £ 8.40m | £ 2.40m | £ 16.80m | £ 4.80m |
31st July 2015 | £ 11.90m | £ 3.60m | £ 23.90m | £ 7.20m |
31st October 2015 | £ 15.50m | £ 3.60m | £ 31.10m | £ 7.20m |
Any date after 30th January 2016 | £ 19.10m | £ 3.60m | £ 38.20m | £ 7.20m |
PART 3Ground source heat pumps
Table 3
Assessment date | Expenditure threshold | Growth threshold | Super expenditure threshold | Super growth threshold |
---|
31st July 2014 | £ 2.40m | - | £ 4.80m | - |
31st October 2014 | £ 4.20m | £ 1.80m | £ 8.40m | £ 3.60m |
31st January 2015 | £ 6.00m | £ 1.80m | £ 12.00m | £ 3.60m |
30th April 2015 | £ 8.40m | £ 2.40m | £ 16.80m | £ 4.80m |
31st July 2015 | £ 11.90m | £ 3.60m | £ 23.90m | £ 7.20m |
31st October 2015 | £ 15.50m | £ 3.60m | £ 31.10m | £ 7.20m |
Any date after 30th January 2016 | £ 19.10m | £ 3.60m | £ 38.20m | £ 7.20m |
PART 4Solar thermal plants
Table 4
Assessment date | Expenditure threshold | Growth threshold | Super expenditure threshold | Super growth threshold |
---|
31st July 2014 | £ 1.20m | - | £ 2.30m | - |
31st October 2014 | £ 2.10m | £ 0.90m | £ 4.10m | £ 1.80m |
31st January 2015 | £ 2.90m | £ 0.90m | £ 5.90m | £ 1.80m |
30th April 2015 | £ 3.90m | £ 1.00m | £ 7.80m | £ 1.90m |
31st July 2015 | £ 5.00m | £ 1.10m | £ 10.00m | £ 2.20m |
31st October 2015 | £ 6.10m | £ 1.10m | £ 12.20m | £ 2.20m |
Any date after 30th January 2016 | £ 7.20m | £ 1.10m | £ 14.40m | £ 2.20m |