xmlns:atom="http://www.w3.org/2005/Atom"

SCHEDULE 2REQUIREMENTS

Construction Environmental Management Plan

13.—(1) No authorised development shall commence until a Construction Environmental Management Plan (“CEMP”) has, after consultation with Natural Resources Wales, been submitted to and approved by the relevant planning authorities. The CEMP must reflect the proposals set out in the draft CEMP set out at appendix 4.2 of volume 3 of the environmental statement including:

(a)traffic and access;

(b)air quality and dust;

(c)ecology and nature conservation;

(d)water protection and management;

(e)noise management;

(f)waste and materials management; and

(g)a complaints procedure.

(2) All construction works must be undertaken in accordance with the approved CEMP, or with such changes to that document as agreed by the relevant planning authorities.