SCHEDULES
SCHEDULE 2REQUIREMENTS
Street lighting
12
1
No part of the authorised development is to commence until a scheme of the lighting to be erected along the link road has been submitted to and approved in writing by the relevant planning authority.
2
The scheme submitted under sub-paragraph (1) must include details ofโ
a
the areas of the link road to be lit;
b
the position of the lighting columns and their heights and designs, including their luminaires and any shielding that is to be incorporated into the lighting columns;
c
the extent of the light spread from each column; and
d
mitigation measures relating to lighting reflecting the proposals in the environmental statement.
3