The Burbo Bank Extension Offshore Wind Farm Order 2014

 Help about what version

What Version

  • Latest available (Revised)
  • Original (As made)

Status:

This is the original version (as it was originally made). This item of legislation is currently only available in its original format.

1.  A nationally significant infrastructure project as defined in sections 14 and 15 of the 2008 Act approximately 7 kilometres off the north Wirral coast, 8.5 kilometres from Crosby beach and 12.2 kilometres off the coast of Point of Ayr, Wales, being an extension to the existing Burbo Bank offshore wind farm located on the bed of Liverpool Bay, comprising—

Work No. 1

(a)an offshore wind turbine generating station with a gross electrical output capacity of up to 259 MW comprising up to 69 wind turbine generators each fixed to the seabed by one of three foundation types (namely steel monopile foundation, gravity base foundation or jacket foundation), fitted with rotating blades and situated within the Order limits and further comprising (b) below;

(b)a network of cables laid underground within the Order limits between the WTGs and Work No. 2, for the transmission of electricity and electronic communications between those different structures;

and associated development within the meaning of section 115(2) of the 2008 Act comprising—

Work No. 2 – up to one offshore substation fixed to the seabed by one of three foundation types (namely steel monopile foundation, gravity base foundation or jacket foundation), within the Order limits;

Work No. 3 – a grid connection from Work No. 2 consisting of up to two cables laid along routes within the Order limits, including one or more cable crossings, to Welsh territorial waters at grid coordinates 53° 25.82′/-3° 21.97′ and 53° 25.99′/-3° 22.32′;

and in connection with such Works No. 1 to 3 and to the extent that they do not otherwise form part of any such work, further associated development comprising such other works as may be necessary or expedient for the purposes of or in connection with the relevant part of the authorised project and which fall within the scope of the work assessed by the environmental statement and the provisions of the deemed marine licences.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources