SCHEDULE 1Authorised project

PART 1Authorised development

HPC Development Site: HPC Accommodation CampusIn the District of West Somerset and the County of Somerset

  • Work No. 3

    An accommodation campus comprising the following works—

    1. a

      site preparation works including construction hoardings, perimeter enclosure, ecological fencing and security; establishment of site construction compounds, construction related buildings, structures, plant, machinery and construction lighting;

    2. b

      earthworks including site levelling, utilities trenches and surface water drainage system;

    3. c

      campus accommodation buildings, amenity building, security buildings, associated structures and plant;

    4. d

      bus stops and associated structures;

    5. e

      sports pitches, WC building, associated structures and plant;

    6. f

      landscape works;

    7. g

      site access, internal access roads, site access from Work No. 1B, servicing yard, emergency access, hardstanding, car, motorcycle and bicycle parking areas;

    8. h

      CCTV poles and mountings, lighting poles and fittings;

    9. i

      perimeter and internal fencing, signage, secured entrance, security building, gates and barriers; and

    10. j

      demolition / removal of buildings, hardstanding areas, parking areas and below ground services; and landscape works pursuant to Work No. 1A(l).

    The location of the above works is shown on sheet no. 5.