5.—(1) The promoter may construct and maintain either Work No. 1A or Work No. 1B (but not both) together with the remainder of the scheduled works.
(2) Subject to article 6 (power to deviate), the scheduled works may only be constructed in the lines or situations shown on the works and land plans and in accordance with the levels shown on the sections.
(3) Subject to paragraph (6), the promoter may carry out and maintain such of the following works as may be necessary or expedient for the purposes of, or for purposes ancillary to, the construction of the scheduled works, namely—
(a)stations, depots, platforms, junctions and stopping places;
(b)buildings and other works required for, or in connection with, the control, management or maintenance of the transport systems or the control or management of any vehicular and pedestrian traffic on or in the transport systems;
(c)works required for the strengthening, improvement, maintenance or reconstruction of any street;
(d)works for the strengthening, alteration or demolition of any building;
(e)works to alter the position of any street furniture or apparatus, including mains, sewers, drains, pipes, cables and lights;
(f)works to alter the course of, or otherwise interfere with, watercourses;
(g)landscaping, ecological and other works to mitigate any adverse effects of the construction, maintenance or operation of the other authorised works; and
(h)facilities and works for the benefit or protection of land or premises affected by the other authorised works.
(4) Subject to paragraph (6), the promoter may carry out and maintain such other works (of whatever nature) as may be necessary or expedient for the purposes of, or for purposes ancillary to, the construction of the scheduled works.
(5) The promoter may remove any works constructed by it under this Order which have been constructed as temporary works or which it no longer requires.
(6) Paragraphs (3) and (4) only authorise the carrying out or maintenance of works—
(a)within the Order limits; or
(b)within the boundaries of any street along which the construction of any part of the transport systems is shown on the works and land plans, or which has a junction with such a street.
(7) The powers conferred by this article must not be exercised within the boundaries of a street outside of the Order limits which has a junction with a street in which the construction of the transport systems is shown on the works and land plans without the consent of the street authority but such consent must not be unreasonably withheld.
(8) The promoter may in constructing or maintaining any part of the harbour railway system which is laid along a street lay down such number of switches and crossings as may be necessary or expedient.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: