SCHEDULE 2Requirements

Controlled water protection scheme

9.—(1) No stage of the authorised development must commence until a controlled water protection scheme has, after consultation with the Environment Agency, been submitted to and approved by the relevant planning authority in relation to that stage. The scheme must include—

(a)measures necessary taking account of the proposed pylon foundations;

(b)any necessary de-watering;

(c)measures to protect water sources; and

(d)measures to protect groundwater dependent terrestrial ecosystems (including the River Nar).

(2) The authorised development must be carried out in accordance with the approved controlled water protection scheme, unless otherwise approved in writing by the relevant planning authority.