The National Grid (King’s Lynn B Power Station Connection) Order 2013

 Help about what version

What Version

  • Latest available (Revised)
  • Original (As made)

Status:

This is the original version (as it was originally made). This item of legislation is currently only available in its original format.

Construction traffic

14.—(1) No stage of the authorised development is to commence until a construction traffic management plan, including details of the following—

(a)the approved routing plans which all drivers of construction vehicles serving towers KL08 and 4VV039 (shown on plan reference MPP00006 - 2 Figure 2A) must use;

(b)the steps to be taken to advise all drivers of vehicles visiting the authorised development of the approved construction routes and of the measures to monitor compliance;

(c)provision for on-site parking for construction workers;

(d)on site wheel cleaning facilities for construction vehicles;

(e)condition survey in relation to the bridge over the River Nar within plot 37 in the book of reference;

(f)“before” and “after” joint road condition surveys in relation to each phase of construction;

(g)strategic route signing;

(h)signing at access points;

(i)access points constructed to allow safe traffic movements;

(j)liaison with the highway authority in respect of its programme of repair and maintenance of the public highway;

(k)road sweeping facilities;

(l)on site dust suppression;

(m)how the local residents and stakeholders are to be kept informed of the construction traffic management plan;

(n)how the construction traffic management plan will be updated as other project programmes are confirmed; and

(o)school hour restrictions in relation to school picking up and dropping off times.

has been, after consultation with the highway authority and the Highways Agency submitted to and approved by the relevant planning authority in relation to that stage.

(2) The authorised development must be carried out in accordance with the approved construction traffic management plan, unless otherwise approved in writing by the relevant planning authority.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources