33.—(1) The energy administrator must prepare a report (the “progress report”) which includes—

(a)details of the court where the proceedings are and the relevant court reference number;

(b)full details of the energy supply company’s name, address of registered office and registered number;

(c)full details of the energy administrator’s name and address, date of appointment and name and address of the applicant for the energy supply company administration application including any changes in office-holder, and, in the case of joint energy administrators, their functions as set out in the statement made for the purposes of section 158(5) of the 2004 Act;

(d)details of progress during the period of the report, including a receipts and payments account (as detailed in paragraph (2) below);

(e)details of any assets that remain to be realised; and

(f)any other relevant information for the creditors.

(2) A receipts and payments account must state what assets of the energy supply company have been realised, for what value, and what payments have been made to creditors or others. The account is to be in the form of an abstract showing receipts and payments during the period of the report and where the energy administrator has ceased to act, the receipts and payments account must include a statement as to the amount paid to unsecured creditors by virtue of the application of section 176A of the 1986 Act (prescribed part).

(3) The progress report must cover—

(a)the period of 6 months commencing on the date that the energy supply company entered energy supply company administration, and every subsequent period of 6 months; and

(b)when the energy administrator ceases to act, any period from the date of the previous report, if any, and from the date that the energy supply company entered energy supply company administration if there is no previous report, until the time that the energy administrator ceases to act.

(4) The energy administrator must send a copy of the progress report, attached to Form ESCA12, within 1 month of the end of the period covered by the report, to—

(a)the Secretary of State;

(b)GEMA;

(c)the creditors; and

(d)the court,

and must deliver a copy to the registrar of companies, but this rule does not apply when the period covered by the report is that of a final progress report under Rule 78.

(5) The court may, on the energy administrator’s application, extend the period of 1 month mentioned in paragraph (4) above, or make such other order in respect of the content of the report as it thinks fit.

(6) It is an offence for the energy administrator to fail to comply with this Rule.

Back to top

Options/Help

Print Options

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open The Whole Instrument without Schedules

The Whole Instrument without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument without Schedules as a PDF

The Whole Instrument without Schedules you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open the Whole Instrument without Schedules

The Whole Instrument without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Impact Assessments

Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:

  • Why the government is proposing to intervene;
  • The main options the government is considering, and which one is preferred;
  • How and to what extent new policies may impact on them; and,
  • The estimated costs and benefits of proposed measures.
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources