4.—(1) No stage of the authorised development is to commence until a written landscaping scheme for that stage has, after consultation with the relevant planning authority, been submitted to, and approved in writing by, the relevant planning authority.
(2) The submitted scheme must reflect the mitigation measures described in section 5.2 (Construction Phase Incorporated Mitigation) of Technical Appendix F (Landscape and Visual Amenity) to Volume II of the environmental statement.
(3) The landscape scheme must include details of—
(a)location, number, species, size and planting density of any proposed planting;
(b)cultivation, importing of materials and other operations to ensure plant establishment;
(c)implementation timetables for all landscaping; and
(d)temporary fencing that complies with current best practice to protect trees and hedgerows adjacent to the works.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: