26.—(1) The Authority may, upon the application by a person who proposes to construct or operate an eligible installation which has not yet been commissioned, grant preliminary accreditation in respect of that eligible installation provided—
(a)any necessary planning permission has been granted; or
(b)such planning permission is not required and appropriate evidence of this is provided to the Authority from the relevant planning authority.
(2) The Authority must not grant preliminary accreditation to any plant under this regulation if, in its opinion, that plant is unlikely to generate heat for which periodic support payments may be paid.
(3) An application for preliminary accreditation must be in writing and supported by such of the information specified in Schedule 1 as the Authority may require.
(4) The Authority may attach such conditions as it considers appropriate in granting preliminary accreditation under this regulation.
(5) Where a plant has been granted preliminary accreditation (and such preliminary accreditation has not been withdrawn) and an application for accreditation is made under this Part, the Authority must, subject to regulation 23, grant that application unless it is satisfied that—
(a)there has been a material change in circumstances since the preliminary accreditation was granted such that, had the application for preliminary accreditation been made after the change, it would have been refused;
(b)any condition attached to the preliminary accreditation has not been complied with;
(c)the information on which the decision to grant the preliminary accreditation was based was incorrect in a material particular such that, had the Authority known the true position when the application for preliminary accreditation was made, it would have been refused; or
(d)there has been a change in applicable legislation since the preliminary accreditation was granted such that, had the application for preliminary accreditation been made after the change, it would have been refused.
(6) Where any of the circumstances mentioned in paragraph (7) apply in relation to a preliminary accreditation which the Authority has granted and having regard to those circumstances the Authority considers it appropriate to do so, the Authority may—
(a)withdraw the preliminary accreditation;
(b)amend the conditions attached to the preliminary accreditation;
(c)attach conditions to the preliminary accreditation.
(7) The circumstances referred to in paragraph (6) are as follows—
(a)in the Authority’s view there has been a material change in circumstances since the preliminary accreditation was granted;
(b)any condition attached to the preliminary accreditation has not been complied with;
(c)the Authority considers that the information on which the decision to grant the preliminary accreditation was based was incorrect in a material particular;
(d)there has been change in the applicable legislation since the preliminary accreditation was granted such that, had the application for preliminary accreditation been made after the change, it would have been refused.
(8) The Authority must send the applicant a notice setting out—
(a)its decision on an application for preliminary accreditation of a plant or on the withdrawal of any preliminary accreditation;
(b)any condition attached to the preliminary accreditation or any amendment to those conditions.
(9) The notice sent pursuant to paragraph (8) must specify the date on which the grant or withdrawal of preliminary accreditation is to take effect and, where applicable, the date on which any conditions (or amendments to those conditions) attached to the preliminary accreditation are to take effect.
(10) In paragraph (1), the reference to the person who proposes to construct an eligible installation includes a person who arranges for the construction of the eligible installation.
(11) This regulation does not apply to a plant which will generate heat using—
(a)a solar collector;
(b)a heat pump which complies with the requirements of regulation 8(a); or
(c)solid biomass, provided that the plant will have an installation capacity below 200kWth.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made):The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: