The Network Rail (Nuneaton North Chord) Order 2010 No. 1721 xmlns:atom="http://www.w3.org/2005/Atom"
Introductory Text
PART 1
1.Citation and commencement
2.Interpretation
3.Incorporation of Railways Clauses Acts
4.Application of the 1991 Act
PART 2
Principal powers
5.Power to construct and maintain works
6.Power to deviate
Streets
7.Power to execute street works
8.Stopping up of street and extinguishment and creation of rights
9.Temporary stopping up of streets
10.Access to works
11.Agreements with street authorities
Specific works
12.Canal Farm Road and Work No. 3: rights
13.Temporary closure of and works in Coventry Canal
Supplemental powers
14.Discharge of water
15.Power to survey and investigate land
PART 3
Powers of acquisition
16.Power to acquire land
17.Application of Part 1 of the Compulsory Purchase Act 1965
18.Application of the Compulsory Purchase (Vesting Declarations) Act 1981
19.Power to acquire new rights
Temporary possession of land
20.Temporary use of land for construction of works
Compensation
21.Disregard of certain interests and improvements
22.Set-off for enhancement in value of retained land
Supplementary
23.Acquisition of part of certain properties
24.Extinction or suspension of private rights of way
25.Time limit for exercise of powers of acquisition
PART 4
26.Defence to proceedings in respect of statutory nuisance
27.Power to lop trees overhanging the authorised works
28.Planning permission and supplementary matters
29.Obstruction of construction of authorised works
30.Statutory undertakers, etc.
31.Protection for specified undertakers
32.Protection for operators of electronic communications code networks
33.Protection for the Environment Agency
34.Certification of plans, etc.
35.Service of notices
36.No double recovery
37.Arbitration
Signature
SCHEDULES
SCHEDULE 1
SCHEDULED WORKS
SCHEDULE 2
STREET TO BE STOPPED UP
SCHEDULE 3
STREETS TO BE TEMPORARILY STOPPED UP
SCHEDULE 4
ACQUISITION OF LAND
PART 1 ACQUISITION OF LAND FOR CONSTRUCTION OF THE AUTHORISED WORKS
PART 2 ACQUISITION OF LAND FOR SPECIFIED PURPOSES
SCHEDULE 5
ACQUISITION OF RIGHTS, ETC.
SCHEDULE 6
MODIFICATION OF COMPENSATION AND COMPULSORY PURCHASE ENACTMENTS FOR CREATION OF NEW RIGHTS
Compensation enactments
1.The enactments for the time being in force with respect...
2.(1) Without limitation on the scope of paragraph 1, the...
Application of the 1965 Act
3.(1) The 1965 Act shall have effect with the modifications...
4.For section 7 of the 1965 Act (measure of compensation)...
5.For section 8 of the 1965 Act (provisions as to...
6.The following provisions of the 1965 Act (which state the...
7.Section 11 of the 1965 Act (powers of entry) shall...
8.Section 20 of the 1965 Act (protection for interests of...
9.Section 22 of the 1965 Act (protection of acquiring authority’s...
SCHEDULE 7
LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN
SCHEDULE 8
STATUTORY UNDERTAKERS, ETC.
Apparatus of statutory undertakers, etc. on land acquired
1.(1) Sections 271 to 274 of the 1990 Act (power...
Apparatus of statutory undertakers, etc. in stopped up street
2.(1) Where a street is stopped up under article 8...
Navigation undertakings
3.(1) Subject to the following provisions of this paragraph, the...
SCHEDULE 9
PROTECTION FOR SPECIFIED UNDERTAKERS
1.(1) For the protection of the undertakers referred to in...
2.In this Schedule— “alternative apparatus” means alternative apparatus adequate to...
3.This Schedule does not apply to apparatus in respect of...
4.Regardless of any provision in this Order or anything shown...
5.(1) If, in the exercise of the powers conferred by...
6.(1) Where, in accordance with the provisions of this Schedule,...
7.(1) Not less than 28 days before starting the execution...
8.(1) Subject to the following provisions of this paragraph, Network...
9.(1) Subject to sub-paragraphs (2) and (3), if by reason...
10.Nothing in this Schedule shall affect the provisions of any...
SCHEDULE 10
PROTECTION FOR OPERATORS OF ELECTRONIC COMMUNICATIONS CODE NETWORKS
1.(1) For the protection of any operator, the following provisions...
2.The temporary stopping up or diversion of any highway under...
3.(1) Subject to sub-paragraphs (2) to (4), if as the...
SCHEDULE 11
PROTECTION FOR THE ENVIRONMENT AGENCY
1.(1) The following provisions shall apply for the protection of...
2.(1) Before beginning to construct any specified work, Network Rail...
3.Without limitation on the scope of paragraph 2, the requirements...
4.(1) Subject to sub-paragraph (2), any specified work, and all...
5.(1) Subject to the provisions of this Schedule and except...
6.Subject to paragraph 8, if by reason of the construction...
7.(1) Network Rail shall take all such measures as may...
8.Nothing in paragraphs 4(4), 5(3), 6, 7(3) and (4) shall...
9.Network Rail shall indemnify the Agency in respect of all...
10.(1) Without affecting the other provisions of this Schedule, Network...
11.The fact that any work or thing has been executed...
12.For the purposes of Chapter 2 of Part 2 of...
13.Any dispute arising between Network Rail and the Agency under...
Explanatory Note