The Site Waste Management Plans Regulations 2008

Updating a site waste management plan for a project of £500,000 or less

This section has no associated Explanatory Memorandum

7.—(1) If the project has an estimated cost of £500,000 or less, whenever waste is removed from the site the principal contractor must record on the site waste management plan—

(a)the identity of the person removing the waste;

(b)the types of waste removed; and

(c)the site that the waste is being taken to.

(2) Within three months of the work being completed the principal contractor must add to the plan—

(a)confirmation that the plan has been monitored on a regular basis to ensure that work is progressing according to the plan and that the plan was updated in accordance with this regulation; and

(b)an explanation of any deviation from the plan.

(3) Failure to comply with this regulation is an offence.