13.—(1) If, during the construction of any specified work, or within 10 years after the completion of such work, there is caused or created an accumulation or erosion or an alteration to tidal flow in the Ouseburn or the River Tyne which adversely affects flood flows or drainage, which is reasonably attributable to the construction, maintenance or operation of such work, the Council shall, if so required by the Environment Agency before, or within the period of 10 years after, such completion and to the extent that it is so attributable, remedy such accumulation or erosion or the effects of such alteration to tidal flow in the manner specified in sub-paragraph (3) and, if it refuses or fails to do so, the Environment Agency may itself cause such remedy to be carried out and may recover the reasonable cost of so doing from the Council.

(2) Should any accumulation or erosion or effect of an alteration to tidal flow arise which adversely affects flood flows or drainage in consequence of such construction, maintenance or operation within the said period of 10 years and be required to be remedied in accordance with sub-paragraph (1), any continuation or recurrence of such accumulation or erosion or effect of an alteration of tidal flow shall, from time to time and to the extent that any accumulation or erosion or effect of an alteration of tidal flow adversely affects flood flows or drainage and is reasonably attributable to the construction, maintenance or operation of any specified work, be so remedied by the Council during the said period of 10 years and at any time thereafter, save that the Council’s obligation under this sub-paragraph shall cease in the event that following the remedying of any accumulation or erosion or effect of alteration of tidal flow a period of 10 years elapses without any further accumulation or erosion or effect of alteration of tidal flow.

(3) For the purposes of sub-paragraphs (1) and (2) above—

(a)in the case of an accumulation, the remedy shall be its removal or such other protective works or measures as may reasonably be required by the Environment Agency;

(b)in the case of erosion, the remedy shall be the carrying out of such reconstruction works and protective measures as may be reasonably required by the Environment Agency; and

(c)in the case of the effects of alteration of tidal flow, the remedy shall be the carrying out of such works and measures as may be reasonably required by the Environment Agency in order to avoid a recurrence of such effects.

(4) To the extent that the Council establishes by surveys, inspections, tests or sampling that such accumulation or erosion or effect of alteration of tidal flow would have been caused in any event by factors other than the construction, maintenance or operation of a specified work the Council shall not be liable to remedy such accumulation or erosion or effect of alteration of tidal flow.

(5) In carrying out any surveys, inspections, tests or sampling under sub-paragraph (4) the Council shall not unreasonably delay the execution of any remedial action required under sub-paragraphs (1) or (2).

(6) The impoundment or release of water by means of the scheduled works shall not of themselves be an effect of alteration of tidal flow for the purposes of this paragraph.

(7) The Council and the Environment Agency shall consult the Port Authority in relation to any action taken under this paragraph with a view to co-ordinating or reconciling any such action with any action taken under paragraph 7.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources