The Marine Works (Environmental Impact Assessment) Regulations 2007

Information required where another application has been made

This section has no associated Explanatory Memorandum

2.  Where the regulated activity is to be carried out in the course of a project in respect of which the applicant has made an application to a consenting authority other than the regulator, an applicant seeking a scoping opinion must—

(a)inform the appropriate authority and the regulator (if the regulator is not also the appropriate authority) of any such application;

(b)if any such consenting authority has requested an environmental statement in respect of that project, inform the appropriate authority and the regulator (if the regulator is not also the appropriate authority) of that request; and

(c)if so requested by the appropriate authority or the regulator, provide the appropriate authority with a copy of any environmental statement and of any other environmental information provided to any such consenting authority.