PART 2REGULATED ACTIVITY IN RELATION TO WHICH AN ENVIRONMENTAL IMPACT ASSESSMENT IS (OR MAY BE) REQUIRED

Determination: Annex II projects8

1

Subject to regulations 9 and 10, the appropriate authority must determine that an environmental impact assessment is required in relation to a regulated activity that is to be carried out in the course of an Annex II project, if it concludes that the project in question is likely, because of its size, nature or location, to have significant effects on the environment.

2

In reaching a conclusion as to whether or not an Annex II project is likely to have significant effects on the environment, the appropriate authority must have regard to the criteria set out in Schedule 1.