Search Legislation

The Network Rail (Thameslink 2000) Order 2006

 Help about what version

What Version

  • Latest available (Revised)
  • Original (As made)

Status:

This is the original version (as it was originally made). This item of legislation is currently only available in its original format.

58.—(1) Before beginning to construct any specified work, Network Rail shall submit to the Agency plans of the work and such further particulars available to it as the Agency may within 28 days of the submission of the plans reasonably require.

(2) Without prejudice to sub-paragraph (1), Network Rail shall ensure that its contractor will provide the Agency with all reasonable necessary hydraulic information in order to identify and quantify any effects of erosion and deposition on the Thames riverbed and foreshore which are likely to be caused by any such specified work (including the use of barges) and such information shall be accompanied by an appropriate assessment of likely effects (such as any consequential loss of foreshore habitat and impacts on river wall stability) and of any remedial measures which may be reasonably necessary having regard to any such likely effects.

(3) Any such specified work shall not be constructed except in accordance with such plans as may be approved in writing by the Agency, or determined under paragraph 69.

(4) Any approval of the Agency required under this paragraph—

(a)shall not be unreasonably withheld;

(b)shall be deemed to have been given if it is neither given nor refused within 2 months of the submission of the plans for approval and, in the case of a refusal, accompanied by a statement of the grounds of refusal; and

(c)may be given subject to such reasonable requirements as the Agency may make for the protection of any drainage work or the fishery or for the protection of water resources, or for the prevention of flooding or pollution and in the discharge of its environmental and recreational duties.

(5) The Agency shall use its reasonable endeavours to respond to the submission of any plans before the expiration of the period mentioned in sub-paragraph (4)(b).

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources