Search Legislation

The Stockton-on-Tees Borough Council North Shore Development (North Shore Footbridge) Scheme 2006 Confirmation Instrument 2006

What Version

 Help about what version
  • Latest available (Revised)
  • Original (As made)

Status:

This is the original version (as it was originally made). UK Statutory Instruments are not carried in their revised form on this site.

Statutory Instruments

2006 No. 2503

HIGHWAYS, ENGLAND

The Stockton-on-Tees Borough Council North Shore Development (North Shore Footbridge) Scheme 2006 Confirmation Instrument 2006

Made

7th September 2006

Coming into force in accordance with article 1

The Secretary of State for Transport makes this Instrument in exercise of powers conferred by section 106(3) of the Highways Act 1980(1) and now vested in him(2):

1.  This Instrument may be cited as The Stockton-on-Tees Borough Council North Shore Development (North Shore Footbridge) Scheme 2006 Confirmation Instrument 2006 and shall come into force on the date on which notice that it has been confirmed is first published in accordance with paragraph 1 of Schedule 2 to the Highways Act 1980.

2.  The Stockton-on-Tees Borough Council North Shore Development (North Shore Footbridge) Scheme 2006 (“the Scheme”) is hereby confirmed without modifications.

3.  The Scheme as confirmed is set out in the Schedule hereto (including the plan) and copies of the Scheme with its accompanying plan are deposited at the offices of the Department for Transport, Floor 13 (IMD), Ashdown House, St Leonards on Sea, Hastings, East Sussex, TN37 7GA, and at the offices of Stockton-on-Tees Borough Council, Municipal Buildings, Church Road, Stockton-on-Tees, TS18 1LD.

Signed by authority of the Secretary of State for Transport

J. Blackie

Regional Director Government Office for the North East

7th September 2006

THE SCHEDULETHE STOCKTON-ON-TEES BOROUGH COUNCIL NORTH SHORE DEVELOPMENT (NORTH SHORE FOOTBRIDGE) SCHEME 2006

The Council of the Borough of Stockton-on-Tees (hereinafter referred to as “the Council” make this Scheme in exercise of their powers under section 106(3) of the Highways Act 1980 and all powers enabling them in that behalf.

1.  The Council are authorised to construct over the navigable waters of the River Tees upstream of the Tees Barage the bridge specified in the Schedule to this Scheme as part of the highway which they are proposing to construct between the South Bank of the River Tees from Grid Point Reference 445396.059-518973.193 to the North Bank of the River Tees Grid Point Reference 445427.520-519150.422.

2.  The Scheme may be cited as The Stockton-on-Tees Borough Council North Shore Development (North Shore Footbridge) Scheme 2006.

  • Given under the common seal of the Council on the 9th day of May 2006

  • EXECUTED as a Deed by

  • Affixing THE COMMON

  • SEAL OF THE COUNCIL OF

  • THE BOROUGH OF

  • STOCKTON-ON-TEES

  • in the presence of

  • Authorised Officer

THE SCHEDULE TO THE SCHEME

1.  The North Shore footbridge forms an important footpath-cycleway link between the proposed North Shore Development and the existing Teesdale site on the South Bank of the River Tees.

2.  The specification of the Structure is as follows:

Plan and Specification to the North Shore Footbridge

The location and general design of the footbridge are shown on the Plan being Job No. 114 Drawing No. 2000 Rev 2 and marked “The Stockton-on-Tees Borough Council North Shore Development (North Shore Footbridge) Scheme 2006” (hereinafter referred to as “the Plan”).

Points of Commencements and Termination

From setting out point Reference SA1 on the South Bank (approximately 107.5 metres from the centre of the University Boulevard Harvard Avenue roundabout) to setting out point Reference NA1 on the North Bank (approximately 56.1 metres from the centre line of the North Shore Road) as indicated on the Plan.

Span

Two spans with an overall distance of 180 metres.

Headway

Not less than 8.0 metres above the Mean Water Level of the River Tees of 2.65 metre AOD within the 62 metre Central Navigation Channel and a minimum of 7.0 metres elsewhere over the river. A minimum headway of 4.0 metres over a 5.0 metre width on the Northbank Promenade, and a minimum headway of 4.0 metres over a 7.5 metre width on the Sounth Bank Promenade.

Waterway

A minimum clear navigable waterway of 93 metres.

Overall Dimensions

The Bridge is designed as an asymmetrical tied double arch. The northern arch will have a span of 120 metres and the southern arch will have a span of 60 metres. A 5.0 metre wide reinforced concrete deck which will provide a footway is suspended on high strength steel cables from the arch. Approach spans comprising a 5.0 metre wide concrete deck on reinforced concrete columns of varying heights are to be constructed on the north and south sides of the mainstructure.

(2)

S.I. 1981/238.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made):The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources