9.—(1) Subject to paragraphs (3) and (5), the amount of electricity generated by a generating station which is to be regarded as having been generated from eligible renewable sources in any month is to be calculated by multiplying the renewable output of that generating station in that month by a proportion which is equal to the proportion which the net output of that generating station in that month bears to the gross output of that generating station in that month.

(2) For the purposes of the calculation referred to in paragraph (1)—

(a)subject to paragraph (6), “the renewable output” is such amount as is obtained by deducting from the gross output of that generating station in that month the amount of electricity which has been generated in that month from fossil fuel; and

(b)“the net output” is such amount as is obtained by deducting from the gross output of that generating station in that month the input electricity of that generating station in that month.

(3) In the case of a generating station fuelled wholly or partly by biomass, 10 per cent of the electricity generated from biomass in any month shall be treated as having been generated from fossil fuel unless the operator of the generating station satisfies the Authority that during that month a lesser percentage of the energy content of the biomass derives from fossil fuel, in which case that lesser percentage shall be treated as having been generated from fossil fuel.

(4) In calculating “the renewable output” in the case of a generating station fuelled partly by fossil fuel and partly by another fuel or fuels the amount of electricity which has been generated from fossil fuel is to be determined according to the respective energy contents of the fuels used.

(5) Where the operator of a generating station satisfies the Authority that in any month the input electricity of the generating station does not exceed 0.5 per cent of its gross output, no input electricity shall be deducted from the gross output in calculating the net output of the generating station for that month and, accordingly, the net output shall be equal to the gross output in that month.

(6) In the case of a qualifying combined heat and power generating station, the renewable output shall be such amount as is obtained by—

(a)deducting from the gross output of that generating station in that month the amount of electricity which has been generated in that month from fossil fuel; and

(b)multiplying the figure resulting from the calculation in sub-paragraph (a) by the relevant proportion.

(7) In this article—

(a)“fossil fuel” has the meaning given to it by section 32 of the Act except that the expression also includes any substance which is derived directly or indirectly from fossil fuel (whether or not such substance is waste or a component of biomass);

(b)“gross output” means, in relation to any month, the total amount of electricity generated by a generating station in that month;

(c)“input electricity” means, in relation to any month, all the electricity used by a generating station in that month (whether or not it is generated by the generating station and whether or not it is used while the generating station is generating electricity) for a purpose directly relating to the operation of that generating station, including fuel handling, fuel preparation, maintenance and pumping water;

(d)in the case of a generating station fuelled wholly or partly by hydrogen (not being fossil fuel), “input electricity” also includes any electricity in respect of which ROCs are or have been issued or which was not generated from eligible renewable sources that is used to produce the hydrogen by which that station is fuelled, regardless of where or by whom the hydrogen is produced;

(e)“qualifying power output” and “total power output” have the meanings given to them in CHPQA; and

(f)“relevant proportion” means a proportion which is equal to the proportion which the qualifying power output of the qualifying combined heat and power generating station bears to the total power output of that generating station.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources