Search Legislation

The Docklands Light Railway (Capacity Enhancement) Order 2005

 Help about what version

What Version

  • Latest available (Revised)
  • Original (As made)

Status:

This is the original version (as it was originally made). This item of legislation is currently only available in its original format.

SCHEDULES

Article 5

SCHEDULE 1SCHEDULED WORKS

In this Schedule—

“the Tower Gateway to Westferry Railway” means that part of the Docklands Light Railway that operates between Tower Gateway Station in the City of London and Westferry Station in the London borough of Tower Hamlets;

“the Poplar to Stratford and Beckton Railway” means that part of the Docklands Light Railway that operates between Poplar Station in the London borough of Tower Hamlets and Stratford and Beckton Stations in the London borough of Newham; and

“the Canary Wharf to Lewisham Railway” means that part of the Docklands Light Railway that operates between Canary Wharf Station in the London borough of Tower Hamlets and Lewisham Station in the London borough of Lewisham.

In the City of London and the London borough of Tower Hamlets

  • Work No. 1—A railway (143 metres in length), being a deviation of the Tower Gateway to Westferry Railway, commencing in the City of London at a point 60 metres north west of the junction of Mansell Street with Royal Mint Street and terminating in the London borough of Tower Hamlets at a point on that railway 150 metres north east of the junction of those streets.

In the London borough of Tower Hamlets

  • Work No. 2—A railway (58 metres in length), being a deviation of the Tower Gateway to Westferry Railway, commencing at a point 93 metres north of the junction of Cable Street with Hardinge Street and terminating at a point on that railway 58 metres east of its commencement.

  • Work No. 3—A railway (99 metres in length), being a deviation of the Poplar to Stratford and Beckton Railway commencing at a point 91 metres north east of the junction of Poplar High Level Walkway with Aspen Way, passing beneath Work No. 5 (footbridge) and terminating at a point on that railway 99 metres east of its commencement.

  • Work No. 4—A railway (90 metres in length), being a deviation of the Poplar to Stratford and Beckton Railway, commencing at a point 90 metres north east of the junction of Poplar High Level Walkway with Aspen Way, passing beneath Work No. 5 (footbridge) and terminating at a point on that railway 90 metres east of its commencement.

  • Work No. 5—A footbridge at Poplar Station incorporating stairs providing a means of emergency escape over the Poplar to Stratford and Beckton Railway, commencing in Aspen Way at a point 12 metres east of the commencement of Work No. 4 (railway) passing over Work Nos. 3 and 4 (railways) and terminating on the Stratford/Beckton bound platform of that station at a point 36 metres east of the commencement of Work No. 3 incorporating a stairway to the footbridge from the Lewisham/Tower Gateway bound platform of that station.

  • Work No. 6—A station constructed on viaduct incorporating pedestrian access, lifts, staircases and new piers to support platforms and canopies commencing on the Canary Wharf to Lewisham Railway at a point 120 metres east of the junction of Millharbour with Marsh Wall, passing over Millwall Cutting and terminating at a point 97 metres east of its commencement.

  • Work No. 7—A railway (112 metres in length) being a realignment of a siding of the Canary Wharf to Lewisham Railway at Mudchute Station commencing at a point 225 metres north of the junction of Thermopylae Gate with Spindrift Avenue and terminating at a point 112 metres south of its commencement.

  • Work No. 8—A railway (176 metres in length) being a deviation of the Canary Wharf to Lewisham Railway commencing at a point 308 metres north of the junction of Spindrift Avenue with Thermopylae Gate and terminating at a point on that railway 132 metres north of that junction.

In the London borough of Newham

  • Work No. 9—A railway (721 metres in length) with sidings forming an extension of Beckton Depot for the stabling and maintenance of rolling stock commencing at a point 135 metres south east of the junction of Royal Docks Road with the Eastern Gateway Grade Separation Bridge and terminating at a point 107 metres east of the south eastern corner of Beckton Depot Engine Shed.

  • Work No. 10—A railway (591 metres in length) with sidings forming an extension of Beckton Depot for the stabling and maintenance of rolling stock commencing at a point 155 metres north east of the junction of Royal Docks Road with the Eastern Gateway Grade Separation Bridge and terminating at a point 108 metres north east of the south eastern corner of Beckton Depot Engine Shed.

Articles 5 and 24

SCHEDULE 2ADDITIONAL LAND WHICH MAY BE ACQUIRED OR USED

PART 1GENERAL

(1)(2)(3)
LocationNumber of land shown on the deposited plansPurpose for which land may be acquired or used
London borough of Tower Hamlets33, 34, 46, 48, 51, 52, 53, 54, 56, 57, 58, 59, 60, 61, 62, 63, 64, 65, 66, 69, 70, 71, 72, 85, 86, 88, 89Pile strengthening, working sites and access
73, 74, 75, 76, 77, 78, 79, 80, 81, 82, 83, 84Pile strengthening and access
91, 92, 95, 96, 97, 98Pile strengthening and access
100, 101, 104, 105, 106, 107, 108, 109, 110, 111, 112, 113, 114, 115, 116Pile strengthening and access
195, 196Pile strengthening and access
203, 204, 205Pile strengthening and access
367, 368, 369, 370, 373, 375, 376, 377, 378, 379, 380, 381, 382, 383, 384, 385, 386, 387, 388Pile strengthening, working site access
489, 490, 491, 492, 494, 495, 496, 497, 498, 501, 502, 503, 504, 505, 506, 540, 541, 543, 544, 545, 546, 547, 548, 549, 578, 579, 580Pile strengthening and access
591Access
594Relocation of vessels
625, 626, 627, 628, 630, 631, 632, 633, 634, 635, 636, 637, 638, 639, 640, 641, 642, 643, 644, 645, 646, 647, 648, 649, 650Pile strengthening, working sites and access

PART 2STATION WORKS

(1)(2)(3)
LocationNumber of land shown on the deposited plansPurpose for which land may be acquired or used
London borough of Tower Hamlets
Shadwell Station127, 128, 129, 130, 131, 132, 133Provision of platform extension, emergency stairs, canopy extension, working sites and access
Limehouse Station219, 220, 221, 222, 223, 224, 226, 227, 228, 229, 230, 231, 232, 233, 234, 235, 236, 237, 238, 239, 240, 241, 242, 243, 245, 246, 247, 248, 249, 250, 251, 253, 254, 255, 256, 257, 259, 260, 261, 262, 263Provision of platform extension, stairs, lift, canopy, substation, pile strengthening, working sites and access
Westferry Station274, 275, 276, 277, 278, 279, 280, 281, 282, 283, 284, 285, 286, 287, 288, 289, 290, 291, 292, 293, 294, 295, 296, 297, 298, 300, 301, 302, 303, 304, 306, 307, 308Provision of platform extension, stairs, lift, canopy, pile strengthening, working sites and access
West India Quay Station394, 395, 396, 398, 399, 400, 401, 402, 403, 404, 405, 406, 407Provision of platform extension, pile strengthening, working sites and access
Crossharbour Station694, 695, 696, 697, 698, 699, 700, 701, 702, 703, 704, 705, 706, 707, 708, 709, 710, 711, 712Provision of platform extension, stairs, canopy extension, pile strengthening, subway, working sites and access
London borough of Greenwich
Greenwich Station737, 739, 740, 741, 743, 744, 745, 748, 749, 750, 751, 752, 753, 754Provision of platform extension, canopy extension, emergency escape stair modifications, removal of existing stairs, pile strengthening, working sites and access
Deptford Bridge Station780, 781Provision of platform extension, canopies, stairs, pile strengthening, working sites and access
London borough of Lewisham
Deptford Bridge Station782, 783, 784, 785, 786, 787, 788, 790, 793Provision of platform extension, canopies, stairs, pile strengthening, working sites and access
Elverson Road800, 804, 805Provision of platform extension, canopies, working sites and access
Lewisham Station822, 823, 824, 825, 827, 828, 830, 831, 832, 833, 834, 835, 836, 837, 838, 839, 840, 841, 842, 843, 844, 845, 846, 847, 848, 851, 852, 853, 854, 855Provision of platform extension, new stairs, stair modifications, structural modifications to existing station, canopy extension

Article 11

SCHEDULE 3STREETS SUBJECT TO STREET WORKS

(1)(2)
AreaStreet subject to street works
London borough of TowerRoyal Mint Street

Hamlets

Back Church Lane

Cable Street

Christian Street

Golding Street

Cannon Street Road

Cornwall Street

Shadwell Place

Sutton Street

Barnardo Street

Butcher Row

Ratcliffe Lane

Bekesbourne Street

Branch Road

Westferry Road

West India Dock Road

Castor Lane

Hertsmere Road

Aspen Way

Private access road (between Aspen Way and Hertsmere Road)

North Colonnade

South Colonnade

Admirals Way

Marsh Wall

Harbour Exchange Square

East Ferry Road

London borough of GreenwichNorman Road
London borough of LewishamJunction Approach

Station Road

Article 12

SCHEDULE 4STREETS TO BE STOPPED UP

PART 1STREETS FOR WHICH A SUBSTITUTE IS TO BE PROVIDED

(1)(2)(3)(4)
AreaStreet affectedExtent of stopping upNew street to be substituted
In the London borough of Tower HamletsWestferry RoadFootpath between points F1 and F2New footpath to be provided between points F1, F3 and F2.
Footpath between points F4 and F5New footpath to be provided between points F4, F6 and F5.
Cycleway (between Westferry Road and Garford Street) between points F3, F2 and C2New cycleway to be provided between points C1 and C2.

PART 2STREETS FOR WHICH NO SUBSTITUTE WILL BE PROVIDED

(1)(2)(3)
AreaStreet to be stopped upExtent of stopping up
In the London borough of Tower HamletsBranch RoadFootways to be narrowed between points N1 and N2 and between points N3 and N4.
Westferry RoadFootway to be stopped up between points F1 and F2 and between points F4 and F5.
Westferry RoadCentral reservation between points N8 and N9.
Westferry RoadFootway to be narrowed between points N5, N6 and N7.
Aspen WayFootway to be stopped up between points P1, P2, P3 and P4.

Article 13

SCHEDULE 5STREETS TO BE TEMPORARILY STOPPED UP

(1)(2)
AreaStreet to be temporarily stopped up
City of London

Minories

Mansell Street

London borough of Tower Hamlets

Mansell Street

Royal Mint Street

Footpath between Chamber Street and Royal Mint Street

Leman Street (East)

Leman Street (West)

Mill Yard

Back Church Lane

Pinchin Street

Cable Street

Christian Street

Golding Street

Cannon Street Road

Cornwall Street

Watney Street

Shadwell Place

Sutton Street

Lukin Street

Johnson Street

Hardinge Street

Devonport Street

Barnardo Street

Bower Street

Stepney Causeway

Pitsea Street

Caroline Street

Ratcliffe Cross Street

Butcher Row

Ratcliffe Lane

Bekesbourne Street

Branch Road

Trinidad Street

Salter Street

Limehouse Causeway

Westferry Road

Private road and cycleway between points F3, F2, C2, C3 and C4

West India Dock Road

Garford Street

Hertsmere Road

Car park access road off Hertsmere Road

Castor Lane

Aspen Way

Private Access Road off Hertsmere Road

Footpath (between Aspen Way and Hertsmere Road)

North Colonnade

West India Avenue

South Colonnade

Churchill Place

Cartier Circle

Trafalgar Way

Fisherman’s Walk

Frobisher Passage

Chancellor Passage

Bank Street

Service road (rear of Heron Quay Station)

Footpath (at South Quay)

Admirals Way

Marsh Wall

Footpath (Millwall Inner Docks)

Harbour Exchange Square

Private Access Roads (London Arena)

Pepper Street

Limeharbour

Selsdon Way

Footway (Limeharbour) between points T1 and T2

Footpath (between Pepper Street and Selsdon Way) between points T3 and T4

East Ferry Road

Footway (East Ferry Road) between points T5 and T6

Spindrift Avenue

London borough of Greenwich

Norman Road

Deptford Bridge

Conington Road

Morden Hill

London borough of Lewisham

Deptford Broadway

Deal’s Gateway

Conington Road

Morden Hill

Junction Approach

Station Road

London borough of NewhamArmada Way

Article 14

SCHEDULE 6ACCESS TO WORKS

(1)(2)
AreaDescription of access
London borough of Tower HamletsRoyal Mint Street

Back Church Lane

Cable Street

Christian Street

Golding Street

Cannon Street Road

Cornwall Street

Shadwell Place

Sutton Street

Butcher Row

Ratcliffe Lane

Bekesbourne Street

Branch Road

West India Dock Road

Castor Lane

Admirals Way

Marsh Wall

East Ferry Road

London borough of GreenwichNorman Road

Article 27

SCHEDULE 7MODIFICATION OF COMPENSATION AND COMPULSORY PURCHASE ENACTMENTS FOR CREATION OF NEW RIGHTS

Compensation enactments

1.  The enactments for the time being in force with respect to compensation for the compulsory purchase of land shall apply, with the necessary modifications as respects compensation, in the case of a compulsory acquisition under this Order of a right by the creation of a new right as they apply as respects compensation on the compulsory purchase of land and interests in land.

2.—(1) Without prejudice to the generality of paragraph 1, the Land Compensation Act 1973(1) shall have effect subject to the modifications set out in sub-paragraphs (2) and (3).

(2) In section 44(1) (compensation for injurious affection), as it applies to compensation for injurious affection under section 7 of the 1965 Act as substituted by paragraph 4—

(a)for the words “land is acquired or taken” there shall be substituted the words “a right over land is purchased”; and

(b)for the words “acquired or taken from him” there shall be substituted the words “over which the right is exercisable”.

(3) In section 58(1) (determination of material detriment where part of house etc. proposed for compulsory acquisition), as it applies to determinations under section 8 of the 1965 Act as substituted by paragraph 5—

(a)for the word “part” in paragraphs (a) and (b) there shall be substituted the words “a right over land consisting”;

(b)for the word “severance” there shall be substituted the words “right over the whole of the house, building or manufactory or of the house and the park or garden”;

(c)for the words “part proposed” there shall be substituted the words “right proposed”; and

(d)for the words “part is” there shall be substituted the words “right is”.

Adaptation of the 1965 Act

3.—(1) The 1965 Act shall have effect with the modifications necessary to make it apply to the compulsory acquisition under this Order of a right by the creation of a new right as it applies to the compulsory acquisition under this Order of land, so that, in appropriate contexts, references in that Act to land are read (according to the requirements of the particular context) as referring to, or as including references to—

(a)the right acquired or to be acquired; or

(b)the land over which the right is or is to be exercisable.

(2) Without prejudice to the generality of sub-paragraph (1), Part I of the 1965 Act shall apply in relation to the compulsory acquisition under this Order of a right by the creation of a new right with the modifications specified in the following provisions of this Schedule.

4.  For section 7 of the 1965 Act (measure of compensation) there shall be substituted the following section:

7.  In assessing the compensation to be paid by the acquiring authority under this Act, regard shall be had not only to the extent (if any) to which the value of the land over which the right is to be acquired is depreciated by the acquisition of the right but also to the damage (if any) to be sustained by the owner of the land by reason of its severance from other land of his, or injuriously affecting that other land by the exercise of the powers conferred by this or the special Act..

5.  For section 8 of the 1965 Act (provisions as to divided land) there shall be substituted the following:—

8.(1) Where in consequence of the service on a person under section 5 of this Act of a notice to treat in respect of a right over land consisting of a house, building or manufactory or of a park or garden belonging to a house (“the relevant land”)—

(a)a question of disputed compensation in respect of the purchase of the right would apart from this section fall to be determined by the Lands Tribunal (“the tribunal”); and

(b)before the tribunal has determined that question the person satisfies the tribunal that he has an interest which he is able and willing to sell in the whole of the relevant land and—

(i)where that land consists of a house, building or manufactory, that the right cannot be purchased without material detriment to that land; or

(ii)where that land consists of such a park or garden, that the right cannot be purchased without seriously affecting the amenity or convenience of the house to which that land belongs;

the Docklands Light Railway (Capacity Enhancement) Order 2005 (“the Order”) shall, in relation to that person, cease to authorise the purchase of the right and be deemed to authorise the purchase of that person’s interest in the whole of the relevant land including, where the land consists of such a park or garden, the house to which it belongs, and the notice shall be deemed to have been served in respect of that interest on such date as the tribunal directs.

(2) Any question as to the extent of the land in which the Order is deemed to authorise the purchase of an interest by virtue of subsection (1) of this section shall be determined by the tribunal.

(3) Where in consequence of a determination of the tribunal that it is satisfied as mentioned in subsection (1) of this section the Order is deemed by virtue of that subsection to authorise the purchase of an interest in land, the acquiring authority may, at any time within the period of six weeks beginning with the date of the determination, withdraw the notice to treat in consequence of which the determination was made; but nothing in this subsection prejudices any other power of the authority to withdraw the notice.

6.  The following provisions of the 1965 Act (which state the effect of a deed poll executed in various circumstances where there is no conveyance by persons with interests in the land), that is to say:—

(a)section 9(4) (failure by owners to convey);

(b)paragraph 10(3) of Schedule 1 (owners under incapacity);

(c)paragraph 2(3) of Schedule 2 (absent and untraced owners); and

(d)paragraphs 2(3) and 7(2) of Schedule 4 (common land);

shall be so modified as to secure that, as against persons with interests in the land which are expressed to be overridden by the deed, the right which is to be compulsorily acquired is vested absolutely in the acquiring authority.

7.  Section 11 of the 1965 Act (powers of entry) shall be so modified as to secure that, as from the date on which the acquiring authority have served notice to treat in respect of any right, they have power, exercisable in the like circumstances and subject to the like conditions, to enter for the purpose of exercising that right (which shall be deemed for this purpose to have been created on the date of service of the notice); and sections 12 (penalty for unauthorised entry) and 13 (entry on warrant in the event of obstruction) of the 1965 Act shall be modified correspondingly.

8.  Section 20 of the 1965 Act (protection for interests of tenants at will, etc.) shall apply with the modifications necessary to secure that persons with such interests in land as are mentioned in that section are compensated in a manner corresponding to that in which they would be compensated on a compulsory acquisition under this Order of that land, but taking into account only the extent (if any) of such interference with such an interest as is actually caused, or likely to be caused, by the exercise of the right in question.

9.  Section 22 of the 1965 Act (protection of acquiring authority’s possession where by inadvertence an estate, right or interest has not been got in) shall be so modified as to enable the acquiring authority, in circumstances corresponding to those referred to in that section, to continue to be entitled to exercise the right acquired, subject to compliance with that section as respects compensation.

Articles 5 and 30

SCHEDULE 8LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN

(1)(2)(3)(4)
Area Number of land shown on the deposited plansPurpose for which temporary possession may be takenAuthorised work
City of London1Working site and accessWork No. 1
London borough of Tower Hamlets55Working site and accessViaduct strengthening
67, 68Working site and accessBridge strengthening
87, 90Working site and accessViaduct strengthening
93, 94Working site and accessBridge strengthening
99Working site and accessBridge strengthening
102, 103Working site and accessViaduct strengthening
117, 118, 119, 120Working site and accessBridge strengthening
121AccessBridge strengthening and viaduct strengthening
122, 123, 124, 125, 126Working site and accessBridge strengthening
134, 135, 136, 137, 138, 139, 140, 141, 142, 143, 144Working site and accessBridge strengthening and viaduct strengthening
150, 151, 152, 153, 154, 155, 156, 157, 158Working site and accessBridge strengthening
159, 160, 161, 162, 163, 164, 165, 166, 167, 168, 169, 170, 171, 172, 173, 174, 175, 176, 177, 178, 179, 180, 181, 182, 183, 184, 185, 186, 187, 188, 189Working sites and accessBridge strengthening
190, 191, 192, 193, 194Working site and accessViaduct strengthening
197, 198Working site and accessStation works, bridge strengthening and viaduct strengthening
199, 200, 201, 202Working site and accessBridge strengthening
206Working siteStation works, bridge strengthening and viaduct strengthening
207, 208, 209, 210Working site and accessBridge strengthening
211, 212, 213, 214, 215, 216, 217, 218Working site and accessStation works, bridge strengthening and viaduct strengthening
225Working site and accessStation works
244, 258Working site and accessStation works
252, 264Working site and accessStation works, bridge strengthening and viaduct strengthening
265, 266, 267, 268, 269, 270, 271, 272, 273Working site and accessStation works
299, 305, 309Working site and accessStation works
310, 311, 312, 313, 314, 315, 316, 317, 318, 319, 320, 321, 322Working site and accessViaduct strengthening
331, 332, 333, 334, 335, 336, 337, 338, 339, 340, 341, 342, 345, 347, 348, 356Working site and accessWork Nos. 3, 4 and 5
323, 324, 325, 326, 327, 328, 329, 330, 351, 352, 353, 357, 358, 359, 360, 361, 362, 363, 364, 365, 366, 371, 372, 374, 389, 390, 391, 392, 393, 397Working site and accessViaduct strengthening
408, 409, 410, 411, 412, 413, 414, 415, 416, 417, 418, 419Working site and accessViaduct strengthening
420, 421, 422, 423, 436, 437, 438, 439, 440, 441, 442, 443, 444, 445, 446, 447, 448, 449, 450, 451, 452, 453, 454, 455, 456, 457, 458, 459, 460, 461, 462, 465, 466, 467, 468, 470Working site and accessViaduct strengthening
424, 425, 426, 427, 428, 429, 430, 431, 432, 433, 434, 435, 463, 464, 469AccessViaduct strengthening
471, 472, 473, 474, 475, 476, 477, 478Working site and accessViaduct strengthening
479, 480, 481, 482, 483, 484, 485, 486, 487, 488, 493, 499, 500, 507, 508, 509, 510, 511, 512, 513, 514, 515, 516, 517, 518, 519, 520, 521, 522, 523, 524, 525, 526, 527, 528, 529, 530, 531, 532, 533, 534, 535, 536, 537, 538, 539, 542, 550, 551, 552, 553, 554, 555, 556, 557, 558, 559, 560, 561, 562, 563, 564, 565, 566Working siteViaduct strengthening
567, 568, 569, 570, 571, 572, 573, 574, 575, 576, 577, 581Working siteDemolition of existing South Quay Station
582, 583, 588, 592, 595, 596, 603, 608, 609, 610, 614, 615, 616, 617, 618, 619, 620Working site and accessWork No. 6 and viaduct strengthening
621, 622, 623, 624, 629, 651, 652, 653, 654, 655, 656, 657, 658, 659, 660, 661, 662, 663, 664, 665, 666, 667, 668, 669, 670, 671, 672, 673, 674, 675, 676, 677, 678, 679, 680, 681, 682, 683, 684, 685, 686, 687, 688, 689, 690, 691, 692, 693Working site and accessViaduct strengthening
713, 714, 715, 716, 717, 718Working site and accessStation works
London borough of Greenwich736, 738, 742, 746, 747, 755, 756, 757Working site and accessStation works
759, 760, 764, 765, 766, 768, 769, 770, 771, 772, 773, 775, 776, 777, 778, 779Working site and accessStation works
806, 807Working siteStation works
London borough of Lewisham758, 761, 762, 763, 767, 774, 789, 791, 792, 794, 795, 796Working site and accessStation works
797, 798, 799, 801, 802, 803, 808, 809, 810, 811, 812, 813, 814, 815, 816, 817, 818, 819, 820, 821, 826, 829, 849, 850, 856Working site and accessStation works
London borough of Newham857, 858, 859, 860, 861, 862, 866, 886, 877, 887AccessWork Nos. 9 and 10

Article 39

SCHEDULE 9PROVISIONS RELATING TO STATUTORY UNDERTAKERS, ETC.

Apparatus of statutory undertakers, etc., on land acquired

1.—(1) Sections 271 to 274 of the 1990 Act (power to extinguish rights of statutory undertakers, etc. and power of statutory undertakers, etc. to remove or re-site apparatus) shall apply in relation to any land acquired or appropriated by DLRL under this Order subject to the following provisions of this paragraph; and all such other provisions of that Act as apply for the purposes of those provisions (including sections 275 to 278, which contain provisions consequential on the extinguishment of any rights under sections 271 and 272, and sections 279(2) to (4), 280 and 282, which provide for the payment of compensation) shall have effect accordingly.

(2) In the provisions of the 1990 Act, as applied by sub-paragraph (1), references to the appropriate Minister are references to the Secretary of State.

(3) Where any apparatus of public utility undertakers or of an electronic communications code operator or former PTO is removed in pursuance of a notice or order given or made under section 271, 272 or 273 of the 1990 Act, as applied by sub-paragraph (1), any person who is the owner or occupier of premises to which a supply was given from that apparatus shall be entitled to recover from DLRL compensation in respect of expenditure reasonably incurred by him, in consequence of the removal, for the purpose of effecting a connection between the premises and any other apparatus from which a supply is given.

(4) Sub-paragraph (3) shall not apply in the case of the removal of a public sewer but where such a sewer is removed in pursuance of such a notice or order as is mentioned in that sub-paragraph, any person who is—

(a)the owner or occupier of premises the drains of which communicated with that sewer; or

(b)the owner of a private sewer which communicated with that sewer,

shall be entitled to recover from DLRL compensation in respect of expenditure reasonably incurred by him, in consequence of the removal, for the purpose of making his drain or sewer communicate with any other public sewer or with a private sewage disposal plant.

(5) The provisions of the 1990 Act mentioned in sub-paragraph (1), as applied by that sub-paragraph, shall not have effect in relation to apparatus as respects which paragraph 2 or Part III of the 1991 Act applies.

(6) In this paragraph—

“public utility undertakers” has the same meaning as in the 1980 Act.

Apparatus of statutory undertakers, etc., in stopped up streets

2.—(1) Where a street is stopped up under articles 12 or 13 of this Order any statutory utility whose apparatus is under, in, upon, over, along or across the street shall have the same powers and rights in respect of that apparatus, subject to the provisions of this paragraph, as if this Order had not been made.

(2) DLRL shall give not less than 28 days' notice in writing of its intention to stop up any street under articles 12 or 13 to any statutory utility whose apparatus is under, in, upon, over, along or across that street.

(3) Where notice under sub-paragraph (2) has been given, any statutory utility whose apparatus is under, in, upon, over, along or across the street may where reasonably necessary for the efficient operation of the undertaking of the statutory utility and, if reasonably requested so to do by DLRL, shall—

(a)remove the apparatus and place it or other apparatus provided in substitution for it in such other position as the statutory utility may reasonably determine and have power to place it; or

(b)provide other apparatus in substitution for the existing apparatus and place it in such position as aforesaid.

(4) Subject to the following provisions of this paragraph, DLRL shall pay to any statutory utility an amount equal to the cost reasonably incurred by the statutory utility in or in connection with:

(a)the execution of relocation works required in consequence of the stopping up of the street; and

(b)the doing of any other work or thing rendered necessary by the execution of relocation works.

(5) If in the course of the execution of relocation works under sub-paragraph (3)—

(a)apparatus of better type, of greater capacity or of greater dimensions is placed in substitution for existing apparatus of worse type, of smaller capacity or of smaller dimensions; or

(b)apparatus (whether existing apparatus or apparatus substituted for existing apparatus) is placed at a depth greater than the depth at which the existing apparatus was,

and the placing of apparatus of that type or capacity or of those dimensions or the placing of apparatus at that depth, as the case may be, is not agreed by DLRL, or, in default of agreement, is not determined by arbitration to be necessary in consequence of the construction of the relocation works, then, if it involves cost in the execution of the relocation works exceeding that which would have been involved if the apparatus placed had been of the existing type, capacity or dimensions, or at the existing depth, as the case may be, the amount which apart from this sub-paragraph would be payable to the statutory utility by virtue of sub-paragraph (4) shall be reduced by the amount of that excess.

(6) For the purposes of sub-paragraph (5)—

(a)an extension of apparatus to a length greater than the length of existing apparatus shall not be treated as a placing of apparatus of greater dimensions than those of the existing apparatus except in a case where the apparatus as so extended provides more than an equivalent service; and

(b)where the provision of a joint in a cable is agreed, or is determined to be necessary, the consequential provision of a jointing chamber or of a manhole shall be treated as if it also had been agreed or had been so determined.

(7) An amount which apart from this sub-paragraph would be payable to a statutory utility in respect of works by virtue of sub-paragraph (4) (and having regard, where relevant, to sub-paragraph (5)) shall, if the works include the placing of apparatus provided in substitution for apparatus placed more than 7 years and 6 months earlier so as to confer on the statutory utility any financial benefit by deferment of the time for renewal of the apparatus in the ordinary course, be reduced by the amount which represents that benefit as calculated in accordance with the Code of Practice entitled “Measures Necessary where Apparatus is Affected by Major Works (Diversionary Works)” and dated June 1992 and approved by the Secretary of State on 30th June, 1992, as revised and re-issued from time to time.

(8) Sub-paragraphs (4) to (7) shall not apply where the authorised works constitute major transport works for the purposes of Part III of the 1991 Act, but instead—

(a)the allowable costs of the relocation works shall be determined in accordance with section 85 of that Act (sharing of costs of necessary measures) and any regulations for the time being having effect under that section; and

(b)the allowable costs shall be borne by DLRL and the statutory utility in such proportions as may be prescribed by any such regulations.

(9) The temporary stopping up, alteration or diversion of any highway under article 13 of this Order shall not affect any right of an electronic communications code operator or a former PTO under paragraph 9 of the electronic communications code in respect of any apparatus which at the time of the stopping up or diversion is in the highway.

(10) In this paragraph—

“apparatus” has the same meaning as in Part III of the 1991 Act;

“relocation works” means works executed, or apparatus provided, under sub-paragraph (3); and

“statutory utility” means a statutory undertaker for the purposes of the 1980 Act or an electronic communications code operator or a former PTO.

3.—(1) Subject to the following provisions of this paragraph, the powers under article 11 of this Order to break up or open a street shall not be exercisable where the street, not being a highway maintainable at public expense (within the meaning of the 1980 Act)—

(a)is under the control or management of, or is maintainable by, railway or tramway undertakers or a navigation authority, or

(b)forms part of a level crossing belonging to any such undertakers or to such an authority or to any other person,

except with the consent of the undertakers or authority or, as the case may be, of the person to whom the level crossing belongs.

(2) Sub-paragraph (1) shall not apply to the carrying out under this Order of emergency works, within the meaning of Part III of the 1991 Act.

(3) A consent given for the purposes of sub-paragraph (1) may be made subject to such reasonable conditions as may be specified by the person giving it but shall not be unreasonably withheld.

(4) In this paragraph “navigation authority” means any person who has a duty or power under any enactment to work, maintain, conserve, improve or control any canal or other inland navigation, navigable river, estuary, harbour or dock.

Article 40

SCHEDULE 10FOR PROTECTION OF NETWORK RAIL INFRASTRUCTURE LIMITED

1.  The following provisions of this Schedule shall, unless otherwise agreed in writing between DLRL and Network Rail Infrastructure Limited, have effect.

2.  In this Schedule—

“C2C” means C2C Limited and includes its successors from time to time;

“SET” means South Eastern Trains Limited and includes its successors from time to time;

“construction” includes execution, placing, alteration and reconstruction and “construct” and “constructed” have corresponding meanings;

“the engineer” means an engineer appointed by Network Rail Infrastructure Limited for the purposes of this Order;

“EWS” means English Welsh and Scottish Railway Limited and includes its successors from time to time;

“network licence” means the network licence, as the same is amended from time to time, granted to Network Rail (then called Railtrack PLC) by the Secretary of Sate in exercise of his powers under section 8 of the 1993 Act;

“Network Rail” means Network Rail Infrastructure Limited and any associated company of Network Rail Infrastructure Limited which holds property for railway purposes, and for the purpose of this definition “associated company” means any company which is (within the meaning of section 736 of the Companies Act 1985(2)) the holding company of Network Rail Infrastructure Limited, a subsidiary of Network Rail Infrastructure Limited or another subsidiary of the holding company of Network Rail Infrastructure Limited;

“plans” includes sections, designs, drawings, specifications, soil reports, calculations, descriptions (including descriptions of methods of construction), staging proposals, programmes and details of the extent, timing and duration of any proposed occupation of railway property;

“railway operational procedures” means procedures specified under any access agreement (as defined in the 1993 Act) or station lease;

“railway property” means any railway belonging to Network Rail Infrastructure Limited and—

(a)

any station, land, works, apparatus and equipment belonging to Network Rail Infrastructure Limited and directly related to any such railway; and

(b)

any easement or other property interest held by or for the benefit of Network Rail and directly related to any such railway;

“relevant costs” means the costs, direct losses and expenses (including loss of revenue) reasonably incurred by each train operator as a consequence of any restriction of the use of Network Rail’s railway network as a result of the construction or failure of a specified work or any such act or omission as mentioned in paragraph 14(1).

“specified work” means so much of any of the authorised works as is situated upon, across, under, over or within 15 metres of, or may in any way adversely affect, railway property; and

“train operator” means any person who is authorised to act as the operator of a train by a licence under section 8 of the 1993 Act.

3.—(1) Subject to paragraph (5), DLRL shall not pursuant to the powers of this Order, without the consent of Network Rail Infrastructure Limited acquire or enter upon, take or use, whether temporarily or permanently or acquire any new rights over any railway property.

(2) DLRL shall not exercise the powers conferred by sections 271 or 272 of the 1990 Act, as applied by Schedule 9 to this Order, in relation to any right of access of Network Rail to railway property, but such right of access may be diverted with the consent of Network Rail Infrastructure Limited.

(3) DLRL shall not in the exercise of the powers conferred by this Order prevent pedestrian or vehicular access to any railway property, unless preventing such access is with the consent of Network Rail Infrastructure Limited.

(4) Where Network Rail Infrastructure Limited is asked to give its consent pursuant to sub-paragraph (1), (2) or (3), such consent shall—

(a)not be unreasonably withheld or delayed but may be given subject to reasonable conditions; and

(b)be subject to compliance by Network Rail Infrastructure Limited with any relevant railway operational procedures.

(5) Nothing in this paragraph shall prevent DLRL pursuant to article 24 of this Order from acquiring the interest of any person other than Network Rail Infrastructure Limited or C2C, EWS or SET in railway property.

4.—(1) DLRL shall before commencing construction of any specified work supply to Network Rail Infrastructure Limited proper and sufficient plans of that work for the reasonable approval of the engineer and the specified work shall not be constructed except in accordance with such plans as have been approved in writing by the engineer or settled by arbitration.

(2) The approval of the engineer under sub-paragraph (1) shall not be unreasonably withheld or delayed, and if by the end of the period of 28 days beginning with the date on which such plans have been supplied to Network Rail Infrastructure Limited the engineer has not intimated his disapproval of those plans and the grounds of his disapproval DLRL may serve upon the engineer written notice requiring the engineer to intimate his approval or disapproval within a further period of 28 days beginning with the date upon which the engineer receives written notice from DLRL. If by the end of the further period of 28 days the engineer has not intimated his approval or disapproval, he shall be deemed to have approved the plans as submitted.

(3) If by the end of the period of 56 days beginning with the date on which written notice was served upon the engineer under sub-paragraph (2) Network Rail Infrastructure Limited gives notice to DLRL that Network Rail Infrastructure Limited desires itself to construct any part of a specified work which in the opinion of the engineer will or may affect the stability of railway property or the safe operation of traffic on the authorised railways then, if DLRL desires such part of the specified work to be constructed, Network Rail Infrastructure Limited shall construct it (together with any adjoining part of the specified work which DLRL reasonably requires to be constructed in one operation with that work) with all reasonable dispatch on behalf of and to the reasonable satisfaction of DLRL in accordance with the plans approved or deemed to be approved or settled under this paragraph and under the supervision (where appropriate and if given) of DLRL.

(4) In the event of Network Rail Infrastructure Limited not constructing or completing any part of a specified work pursuant to sub-paragraph (3) with all reasonable dispatch and to the reasonable satisfaction of DLRL in accordance with such programme as may be agreed with DLRL or settled by arbitration, Network Rail Infrastructure Limited shall pay compensation to DLRL for any loss which it may sustain as a result.

(5) When signifying his approval of the plans the engineer may specify any protective works (whether temporary or permanent) which in his opinion should be carried out before the commencement of a specified work to ensure the safety or stability of railway property or the continuation of safe and efficient operation of the railways of Network Rail Infrastructure Limited or the services of operators using the same (including any relocation of works, apparatus and equipment necessitated by a specified work), and such protective works as may be reasonably necessary for those purposes shall be constructed by Network Rail Infrastructure Limited or by DLRL, if Network Rail Infrastructure Limited so desires, with all reasonable dispatch and DLRL shall not commence the construction of the specified works until the engineer has notified DLRL that the protective works have been completed to his reasonable satisfaction.

5.—(1) Any specified work shall, when commenced, be constructed—

(a)with all reasonable dispatch in accordance with the plans approved or deemed to have been approved or settled under paragraph 4;

(b)under the supervision (where appropriate and if given) and to the reasonable satisfaction of the engineer;

(c)in such manner as to cause as little damage as is possible to railway property; and

(d)so far as is reasonably practicable and consistent with the efficient and economic construction and operation of the specified work, so as not to interfere with or obstruct the free, uninterrupted and safe use of the authorised railways or the traffic thereon and the use by passengers of railway property,

and, if any damage to railway property or any such interference or obstruction is caused or takes place in consequence of the construction of a specified work, DLRL shall, notwithstanding any such approval, make good such damage and shall pay to Network Rail Infrastructure Limited all reasonable expenses to which Network Rail maybe put and compensation for any loss which it may sustain by reason of any such damage, interference or obstruction.

(2) Nothing in this Schedule shall impose any liability on DLRL with respect to any damage, costs, expenses or loss attributable to the negligence of Network Rail or its servants, contractors or agents.

6.  DLRL shall—

(a)at all times afford reasonable facilities to the engineer for access to a specified work during its construction; and

(b)supply the engineer with all such information as he may reasonably require with regard to a specified work or the method of constructing it.

7.  Network Rail Infrastructure Limited shall at all times afford reasonable facilities to DLRL and its agents for access to any works carried out by Network Rail Infrastructure Limited under this Schedule during their construction and shall supply DLRL with such information as it may reasonably require with regard to such works or the method of constructing them.

8.—(1) If any alterations or additions, either permanent or temporary, to railway property are reasonably necessary during the construction of a specified work, or during a period of 12 months after the commencement of regular revenue-earning train operations using the new railways comprised in any specified work, in consequence of the construction of a specified work, and Network Rail Infrastructure Limited gives to DLRL reasonable notice of its intention specifying the alterations or additions to be carried out, DLRL shall pay to Network Rail Infrastructure Limited the reasonable cost of those alterations or additions including, in respect of any such alterations and additions as are to be permanent, a capitalised sum representing the increase of the costs which may be expected to be reasonably incurred by Network Rail Infrastructure Limited in maintaining, working and, when necessary, renewing any such alterations or additions.

(2) If the cost of maintaining, working or renewing railway property is reduced in consequence of any such alterations or additions a capitalised sum representing such saving shall be set off against any sum payable by DLRL to Network Rail Infrastructure Limited under this paragraph.

9.  DLRL shall repay to Network Rail Infrastructure Limited all reasonable fees, costs, charges and expenses reasonably incurred by Network Rail Infrastructure Limited—

(a)in constructing any part of a specified work on behalf of DLRL as provided by paragraph 4(4) or in constructing any protective works under the provisions of paragraph 4(6) including, in respect of any permanent protective works, a capitalised sum representing the cost of maintaining and renewing those works; and

(b)in respect of the approval by the engineer of plans submitted by DLRL and the supervision by him of the construction of a specified work.

10.—(1) In this paragraph—

“EMI” means, subject to sub-paragraph (2), electromagnetic interference with Network Rail’s apparatus generated by the operation of the authorised works where such interference is of a level which adversely affects the safe operation of Network Rail’s apparatus; and

“Network Rail’s apparatus” means any lines, circuits, wires, apparatus or equipment (whether or not modified or installed as part of the authorised works) which are owned or used by Network Rail for the purpose of transmitting or receiving electrical energy or of radio, telegraphic, telephonic, electric, electronic or other like means of signalling or other communications.

(2) This paragraph shall apply to EMI only to the extent that such EMI is not attributable to any change to Network Rail’s apparatus carried out after approval of plans under paragraph 4(1) for the relevant part of the authorised works giving rise to EMI (unless DLRL has been given notice in writing before the approval of those plans of the intention to make such change).

(3) Subject to sub-paragraph (5), DLRL shall in the design and construction of the authorised works take all measures necessary to prevent EMI and shall establish with Network Rail Infrastructure Limited (both parties acting reasonably) appropriate arrangements to verify their effectiveness.

(4) In order to facilitate DLRL’s compliance with sub-paragraph (3)—

(a)DLRL shall consult with Network Rail Infrastructure Limited as early as reasonably practicable to identify all Network Rail’s apparatus which may be at risk of EMI, and thereafter shall continue to consult with Network Rail Infrastructure Limited (both before and after formal submission of plans under paragraph 4(1)) in order to identify all potential causes of EMI and the measures required to eliminate them;

(b)Network Rail Infrastructure Limited shall make available to DLRL all information in Network Rail Infrastructure Limited’s possession reasonably requested by DLRL in respect of Network Rail’s apparatus identified pursuant to sub-paragraph (a); and

(c)Network Rail Infrastructure Limited shall allow DLRL reasonable facilities for the inspection of Network Rail’s apparatus identified pursuant to sub-paragraph (a).

(5) In any case where it is established that EMI can only reasonably be prevented by modifications to Network Rail’s apparatus, Network Rail Infrastructure Limited shall not withhold its consent unreasonably to modifications of Network Rail’s apparatus, but the means of prevention and the method of their execution shall be selected in the reasonable discretion of Network Rail Infrastructure Limited, and in relation to such modifications paragraph 4(1) shall have effect subject to this sub-paragraph.

(6) If at any time prior to the commencement of regular revenue-earning train operations on the new railways comprised in the authorised works and notwithstanding any measures adopted pursuant to sub-paragraph (3), the testing or commissioning of the authorised works causes EMI then DLRL shall immediately upon receipt of notification by Network Rail of such EMI either in writing or communicated orally (such oral communication to be confirmed in writing as soon as reasonably practicable after it has been issued) forthwith cease to use (or procure the cessation of use of) DLRL’s apparatus causing such EMI until all measures necessary have been taken to remedy such EMI by way of modification to the source of such EMI or (in the circumstances, and subject to the consent, specified in sub-paragraph (5)) to Network Rail’s apparatus.

(7) In the event of EMI having occurred—

(a)DLRL shall afford reasonable facilities to Network Rail Infrastructure Limited for access to DLRL’s apparatus in the investigation of such EMI;

(b)Network Rail Infrastructure Limited shall afford reasonable facilities to DLRL for access to Network Rail’s apparatus in the investigation of such EMI; and

(c)Network Rail Infrastructure Limited shall make available to DLRL any additional material information in its possession reasonably requested by DLRL in respect of Network Rail’s apparatus or such EMI.

(8) Where Network Rail Infrastructure Limited approves modifications to Network Rail’s apparatus pursuant to sub-paragraphs (5) or (6)—

(a)Network Rail Infrastructure Limited shall allow DLRL reasonable facilities for the inspection of the relevant part of Network Rail’s apparatus;

(b)any modifications to Network Rail’s apparatus approved pursuant to those sub-paragraphs shall be carried out and completed by DLRL in accordance with paragraph 5.

(9) To the extent that it would not otherwise do so, the indemnity in paragraph 14(1) shall apply to the costs and expenses reasonably incurred or losses suffered by Network Rail through the implementation of the provisions of this paragraph (including costs incurred in connection with the consideration of proposals, approval of plans, supervision and inspection of works and facilitating access to Network Rail’s apparatus) or in consequence of any EMI to which sub-paragraph (6) applies.

(10) For the purpose of paragraph (8)(a) any modifications to Network Rail’s apparatus under this paragraph shall be deemed to be protective works referred to in that paragraph.

(11) In relation to any dispute arising under this paragraph the reference in article 54 of this Order to the Institution of Civil Engineers shall be read as a reference to the Institution of Electrical Engineers.

11.  If at any time after the completion of a specified work, not being a work vested in Network Rail, Network Rail Infrastructure Limited gives notice to DLRL informing it that the state of maintenance of the specified work appears to be such as adversely affects the operation of railway property, DLRL shall, on receipt of such notice, take such steps as may be reasonably necessary to put that specified work in such state of maintenance as not adversely to affect railway property.

12.  DLRL shall not provide any illumination or illuminated sign or signal on or in connection with a specified work in the vicinity of any railway belonging to Network Rail Infrastructure Limited unless it shall have first consulted Network Rail Infrastructure Limited and it shall comply with Network Rail Infrastructure Limited’s reasonable requirements for preventing confusion between such illumination or illuminated sign or signal and any railway signal or other light used for controlling, directing or securing the safety of traffic on the railway.

13.  Any additional expenses which Network Rail Infrastructure Limited may reasonably incur in altering, reconstructing or maintaining railway property under any powers existing at the making of this Order by reason of the existence of a specified work shall, provided that 56 days' previous notice of the commencement of such alteration, reconstruction or maintenance has been given to DLRL, be repaid by DLRL to Network Rail Infrastructure Limited.

14.—(1) DLRL shall pay to Network Rail Infrastructure Limited all reasonable costs, charges, damages and expenses not otherwise provided for in this Schedule which may be occasioned to or reasonably incurred by Network Rail Infrastructure Limited—

(a)by reason of the construction or maintenance of a specified work or the failure thereof; or

(b)by reason of any act or omission of DLRL or of any person in its employ or of its contractors or others whilst engaged upon a specified work;

and DLRL shall indemnify Network Rail Infrastructure Limited from and against all claims and demands arising out of or in connection with a specified work or any such failure, act or omission; and the fact that any act or thing may have been done by Network Rail Infrastructure Limited on behalf of DLRL or in accordance with plans approved by the engineer or in accordance with any requirement of the engineer or under his supervision shall not (if it was done without negligence on the part of Network Rail Infrastructure Limited or of any person in its employ or of its contractors or agents) excuse DLRL from any liability under the provisions of this sub-paragraph.

(2) Network Rail Infrastructure Limited shall give DLRL reasonable notice of any such claim or demand and no settlement or compromise of such a claim or demand shall be made without the prior consent of DLRL.

(3) The sums payable by DLRL under sub-paragraph (1) shall include a sum equivalent to the relevant costs.

(4) Subject to the terms of any agreement between Network Rail Infrastructure Limited and a train operator regarding the timing or method of payment of the relevant costs in respect of that train operator, Network Rail Infrastructure Limited shall promptly pay to each train operator the amount of any sums which Network Rail Infrastructure Limited receives under sub-paragraph (3) which relates to the relevant costs of that train operator.

(5) The obligation under sub-paragraph (3) to pay Network Rail Infrastructure Limited the relevant costs shall, in the event of default, be enforceable directly by any train operator concerned to the extent that such sums would be payable to that operator pursuant to sub-paragraph (4).

15.  Network Rail Infrastructure Limited shall, on receipt of a request from DLRL, from time to time provide DLRL free of charge with written estimates of the costs, charges, expenses and other liabilities for which DLRL is or will become liable under this Schedule (including the amount of the relevant costs mentioned in paragraph 14) and with such information as may reasonably enable DLRL to assess the reasonableness of any such estimate or claim made or to be made pursuant to this Schedule (including any claim relating to those relevant costs).

16.  In the assessment of any sums payable to Network Rail under this Schedule there shall not be taken into account any increase in the sums claimed that is attributable to any action taken by or any agreement entered into by Network Rail if that action or agreement was not reasonably necessary and was taken or entered into with a view to obtaining the payment of those sums by DLRL under this Schedule or increasing the sums so payable.

17.  DLRL and Network Rail Infrastructure Limited may subject in the case of Network Rail Infrastructure Limited to compliance with the terms of its network licence enter into, and carry into effect, agreements for the transfer to DLRL of—

(a)any railway property shown on the deposited plans and described in the book of reference;

(b)any lands, works or other property held in connection with any such railway property; and

(c)any rights and obligations (whether or not statutory) of Network Rail relating to any railway property.

18.  In so far as any specified work or the acquisition or use of railway property is or may be subject to railway operational procedures, Network Rail, SET, EWS and C2C shall—

(a)co-operate with DLRL with a view to avoiding delay and securing conformity as between any plans approved by the engineer and any requirements resulting from those procedures; and

(b)use best endeavours to avoid any conflict arising between the application of railway operational procedures and the proper implementation of the authorised works pursuant to this Order.

Article 41

SCHEDULE 11FOR PROTECTION OF LOCAL HIGHWAY AUTHORITIES

1.  The following provisions of this Schedule shall, unless otherwise agreed in writing between DLRL and the appropriate Council, have effect.

2.  In this Schedule—

“the appropriate Council” means—

(i)

the Corporation of the City of London, in relation to any authorised work constructed in the area of that council; or

(ii)

the Council of the London borough of Tower Hamlets, in relation to any authorised work constructed in the area of that council; or

(iii)

the Council of the London borough of Greenwich, in relation to any authorised work constructed in the area of that council; or

(iv)

the Council of the London borough of Lewisham, in relation to any authorised work constructed in the area of that council.

“highway” means a street vested in or maintainable by the appropriate Council; and

“highway operations” means the construction of any part of the authorised works which will involve interference with a highway or the traffic in a highway and any temporary stopping up, alteration or diversion of a highway.

3.  Before commencing to construct any scheduled work DLRL shall consult the appropriate Council about—

(a)the programme for the construction of that work so as to secure, so far as may be reasonably practicable, that the duration of any disturbance occasioned by, or in connection with, such construction shall be reduced to a minimum; and

(b)the land within the Order limits to be occupied and used by DLRL as temporary working sites for the purpose of such construction, the period for which and the manner in which each site shall be used and the steps to be taken by DLRL in order to mitigate any injury to amenity.

4.  DLRL shall consult the appropriate Council as to—

(a)the routes in the appropriate Council’s area proposed to be used by vehicles, machinery and plant, passing to or from any works under construction; and

(b)the proposed manner and method of disposing of any soil or waste material resulting from the carrying out of any operation in connection with the authorised works;

and such soil or waste material shall not be disposed of by DLRL in the appropriate Council’s area in any manner as shall be objected to in writing by the appropriate Council.

5.  Before commencing to construct any authorised work which will involve highway operations, DLRL shall consult the appropriate Council as to the time when that work will be commenced, as to the extent of the surface of the highway which it may be reasonably necessary for DLRL to occupy in the construction of that work, and as to the conditions under which that work shall be constructed so as not to cause so far as possible inconvenience to the public and to ensure the safety of the public.

6.  Any such highway shall be reinstated by DLRL in a manner reasonably approved by the appropriate Council and to its reasonable satisfaction.

7.  DLRL shall not, except with the consent of the appropriate Council, deposit any soil, subsoil or materials or stand any vehicle or plant on any highway (except on so much thereof as is for the time being temporarily stopped up or occupied under the powers of this Order) so as to obstruct the use of such highway by any person or, except with the like consent, deposit any soil, subsoil or materials on any highway except within a hoarding.

8.  Except in an emergency or where reasonably necessary to secure the safety of the public no direction or instruction shall be given by the appropriate Council to the contractors, servants or agents of DLRL regarding any highway operations without the prior consent in writing of DLRL; but the appropriate Council shall not be liable for any additional costs which may be incurred as a result of the giving of instructions or directions pursuant to this paragraph.

9.  DLRL shall, if reasonably so required by the appropriate Council, provide and maintain during such time as DLRL may occupy any part of a highway for the purpose of the construction of any part of the authorised works, temporary ramps for vehicular traffic or pedestrian traffic, or both, and any other traffic measures required to protect the safety of road users in accordance with the standard recommended in Chapter 8 of the Traffic Signs Manual issued for the purposes of the Traffic Signs Regulations and General Directions 1994(3) in such position as may be necessary to prevent undue interference with the flow of traffic in any highway.

10.  DLRL shall indemnify the appropriate Council against any claim which may arise as a result of any subsidence of, or damage to, any highway or any retained sanitary convenience, refuge, sewer, drain, lamp column, traffic sign, bollard, bin for refuse or road materials or apparatus connected therewith or any other property or work belonging to, or under the jurisdiction or control of, the appropriate Council on or under any highway, or maintainable by them, which may be caused by, or in consequence of, any act or default of DLRL, its contractors, servants or agents but the appropriate Council shall give to DLRL reasonable notice of any such claim and no settlement or compromise of it shall be made without DLRL’s prior consent.

11.  Wherever in this Schedule provision is made with respect to the approval or consent of the appropriate Council, that approval or consent shall be in writing and may be given subject to such reasonable terms and conditions as the appropriate Council may require in the interests of safety and in order to minimise inconvenience to persons using the highway, but shall not be unreasonably withheld.

12.  Any difference arising between DLRL and the appropriate Council under this Schedule (other than a difference as to its meaning or construction) shall be determined by arbitration in accordance with article 54 of this Order.

Article 42

SCHEDULE 12FOR PROTECTION OF THE ENVIRONMENT AGENCY

1.  The following provisions of this Schedule shall, unless otherwise agreed in writing between DLRL and the Environment Agency, (in this Schedule referred to as “the Agency”), have effect.

2.  In this Schedule—

“construction” includes execution, placing, altering, replacing, relaying and, in relation to temporary works, removal; and “construct” and “constructed” shall be construed accordingly;

“damage” includes scouring, erosion and environmental damage and “damaged” shall be construed accordingly;

“drainage work” means any watercourse and includes any land used for providing flood storage capacity for any watercourse and any bank, wall, embankment or other structure or appliance constructed or used for defence against water or for the drainage of land;

“the fishery” means fish in the River Ravensbourne and the spawn, habitat or food of such fish;

“plans” includes sections, drawings, specifications and method statements;

“specified work” means so much of any work or operation authorised by this Order (other than works required in an emergency) as is in, on, under, over or within 16 metres of a drainage work or is otherwise likely to—

(a)

affect any drainage work or the volumetric flow of water in or flowing to or from any drainage work,

(b)

affect the flow, purity or quality of water in any watercourse or other surface waters or groundwater,

(c)

cause obstruction to the free passage of fish or damage to any fishery, or

(d)

affect the conservation, distribution or use of water resources; and

“watercourse” has the meaning given in section 72 of the Land Drainage Act 1991(4).

3.—(1) Before beginning to construct any specified work, DLRL shall submit to the Agency plans of the work and such further particulars available to it as the Agency may reasonably require.

(2) Any such specified work shall not be constructed except in accordance with such plans as may be approved in writing by the Agency, or settled in accordance with paragraph 11 and, where applicable, in accordance with any requirements specified under paragraph 3(3).

(3) Any approval of the Agency required under this paragraph—

(a)shall not be unreasonably withheld or delayed;

(b)shall be deemed to have been given if it is neither given nor refused within 2 months of the submission of plans for approval in writing and, in the case of a refusal, accompanied by a statement of the grounds of refusal;

(c)may be given subject to such reasonable requirements as the Agency may impose for the protection of any drainage work or the fishery or water resources, for the prevention of flooding or water pollution and in the discharge of its environmental and recreational duties.

4.  Without prejudice to the generality of paragraph 3, the requirements which the Agency may impose under that paragraph include conditions requiring DLRL at its own expense to construct such protective works, whether temporary or permanent, during the construction of the specified works (including the provision of flood banks, walls or embankments or other new works and the strengthening, repair or renewal of existing banks, walls or embankments) as are reasonably necessary to safeguard any drainage work against damage or to secure that its efficiency for flood defence purposes is not impaired and that the risk of flooding is not otherwise increased by reason of any specified work.

5.—(1) Any specified work, and all protective works required by the Agency under paragraph 4, shall be constructed to the reasonable satisfaction of the Agency and the Agency shall be entitled by its officer to watch and inspect the construction of such works.

(2) DLRL shall give to the Agency not less than 14 days' notice in writing of its intention to commence construction of any specified work and notice in writing of its completion not later than 7 days after the date on which it is brought into use.

(3) If any part of the works comprising a structure in, over or under a watercourse or within 16 metres of a drainage work is constructed otherwise than in accordance with the requirements of this Schedule, the Agency may by notice in writing require DLRL, at DLRL’s own expense, to comply with the requirements of this Schedule or (if DLRL so elects and the Agency in writing consents, such consent not to be unreasonably withheld) to remove, alter or pull down the work and, where removal is required, to restore the site to its former condition to such extent and within such limits as the Agency reasonably requires.

(4) Subject to sub-paragraph (5), if within a reasonable period, being not less than 28 days from the date when notice under sub-paragraph (3) is served upon DLRL, it has failed to begin taking steps to comply with the requirements of the notice and thereafter to make reasonably expeditious progress towards their implementation, the Agency may execute the works specified in the notice and any expenditure incurred by it in so doing shall be recoverable from DLRL.

(5) In the event of any dispute as to whether sub-paragraph (3) is applicable to any work in respect of which a notice has been served under that sub-paragraph, or as to the reasonableness of any requirement of such a notice, the Agency shall not except in an emergency exercise the powers conferred by sub-paragraph (4) until the dispute has been determined.

6.  If by reason of the construction of any specified work or of the failure of any such work the efficiency of any drainage work for flood defence purposes is impaired, or that work is otherwise damaged, such impairment or damage shall be made good by DLRL to the reasonable satisfaction of the Agency and, if DLRL fails to do so, the Agency may make good the same and recover from DLRL the expense reasonably incurred by it in so doing.

7.—(1) Without prejudice to the other provisions of this Schedule, DLRL shall take all such measures as may be reasonably practicable to prevent any interruption in the passage of fish during the construction of any specified work.

(2) If by reason of—

(a)the construction of any specified work, or

(b)the failure of any such work,

damage to the fishery is caused, or the Agency has reasonable grounds to believe to expect that such damage shall be caused, the Agency may serve notice on DLRL requiring it to take such steps as may be reasonably practicable to make good the damage or, as the case may be, to protect the fishery against such damage.

(3) If, within such time as may be reasonably practicable for that purpose after the receipt of written notice from the Agency of any damage or expected damage to the fishery, DLRL fails to take such steps as are described in sub-paragraph (2), the Agency may take those steps and may recover from DLRL the expense reasonably incurred by it in doing so.

8.  DLRL shall indemnify the Agency in respect of all costs, charges and expenses which the Agency may reasonably incur or have to pay or which it may sustain—

(a)in the examination or approval of plans and reports under this Schedule,

(b)in the inspection of the construction of the specified works or any protective works required by the Agency under this Schedule.

9.—(1) Without prejudice to the other provisions of this Schedule, DLRL shall indemnify the Agency from all claims, demands, proceedings, costs, damages or expenses or loss which may be made or taken against, or recovered from the Agency by reason of—

(a)any damage to any drainage work so as to impair its efficiency for the purposes of flood defence,

(b)any damage to the fishery,

(c)any raising of the water table in land adjoining the works or any sewers, drains and watercourses,

(d)any flooding or increased flooding of any such lands, or

(e)inadequate water quality in any watercourse or other surface waters or in groundwater,

which is caused by the construction of any of the works or any act or omission of DLRL, its contractors, agents, or employees whilst engaged upon any such work.

(2) The Agency shall give DLRL reasonable notice of any such claim or demand and no settlement or compromise thereof shall be made without the agreement of DLRL, which agreement shall not be unreasonably withheld.

10.—(1) The fact that any work or thing has been executed or done in accordance with a plan approved or deemed to be approved by the Agency, or to its satisfaction, or in accordance with any directions or award by an arbitrator, shall not relieve DLRL from any liability under the provisions of this Schedule.

(2) Sub-paragraph (1) shall not apply to the extent that such liability arises from a failure by the Agency properly to perform its functions.

11.  Any difference arising between DLRL and the Agency under this Schedule (other than a difference as to its meaning or construction) shall be determined by arbitration in accordance with article 54 of this Order.

Article 43

SCHEDULE 13FOR PROTECTION OF SPECIFIED UNDERTAKERS

Interpretation

1.  In this Schedule—

“apparatus” means—

(a)

in the case of a specified undertaker which is an electricity undertaker, electric lines or electrical plant (as defined in the Electricity Act 1989(5)) belonging to, or maintained by, that undertaker;

(b)

in the case of a specified undertaker which is a gas undertaker, mains, pipes or other apparatus belonging to, or maintained by, a public gas transporter for the purposes of the transportation and storage of gas;

(c)

in the case of a specified undertaker which is a water undertaker, mains, pipes or other apparatus belonging to, or maintained by, the undertaker for the purposes of water supply; and

(d)

in the case of a specified undertaker which is a sewerage undertaker,

(i)

any drain or works vested in the undertaker under the Water Industry Act 1991(6); and

(ii)

any sewer which is so vested or is the subject of a notice of intention to adopt given under section 102(4) of that Act or an agreement to adopt made under section 104 of that Act;

and includes a sludge main, disposal main (within the meaning of section 219 of that Act) or sewer outfall and any manholes, ventilating shafts, pumps or other accessories forming part of any such sewer, drain or works,

and includes any structure for the lodging therein of apparatus or for giving access to such apparatus;

“construction” includes execution, placing, altering, replacing, relaying and removal and, in its application to works which include or comprise any operation, means the carrying out of that operation;

“emergency works” has the same meaning as in section 52 of the 1991 Act;

“in”, in a context referring to apparatus in land, includes under, over, across, along or upon land;

“necessary alternative apparatus” means alternative apparatus adequate to enable a specified undertaker to fulfil its statutory or licensed functions in a manner no less efficient than previously;

“plans” includes sections, specifications and method statements;

“specified work” means any of the authorised works which—

(a)

will or may be situated over, or within 15 metres measured in any direction of, or may in any way adversely affect, any apparatus; or

(b)

wherever situated, imposes any load upon any sewer;

the removal of which has not been required under paragraph 8; and

“specified undertaker” means—

(a)

EDF Energy plc whose registered office is situated at 40 Grosvenor Place, Victoria, London SW1X 7EN;

(b)

National Grid Transco Plc, whose registered office is 1–3 Strand, London WC2N 5EH; and

(c)

Thames Water Utilities Limited whose registered office is situated at Cleanwater House, Vastern Road, Reading RG1 8DB.

or any person succeeding any such company as a licence holder within the meaning of Part I of the Electricity Act 1989(7), a public gas transporter within the meaning of Part I of the Gas Act 1986(8), a water undertaker within the meaning of the Water Industry Act 1991(9) or as a sewerage undertaker within the meaning of Part I of that Act, and “the specified undertaker” in relation to any apparatus means the specified undertaker to whom the apparatus belongs or by whom it is maintained.

Application of Schedule 9

2.  Paragraphs 1(1) and 2 of Schedule 9 to this Order shall not apply in relation to a specified undertaker and paragraphs 1(3) and 1(4) of that Schedule shall have effect as if they referred to apparatus removed under this Schedule.

Apparatus in stopped up streets

3.  Where any street is stopped up under article 12 of this Order, any specified undertaker whose apparatus is in the street shall have the same powers and rights in respect of that apparatus as it enjoyed immediately before the stopping up, but nothing in this paragraph shall affect any right of DLRL or of the specified undertaker to require the removal of that apparatus under paragraph 8 or the power of DLRL to carry out works under paragraphs 19 to 28.

4.  DLRL shall give not less than 28 days' notice in writing of its intention to stop up any street under article 12 of this Order to any specified undertaker whose apparatus is in that street.

On-street apparatus

5.  This Schedule shall not apply to anything done or proposed to be done in relation to or affecting any apparatus in so far as the relations between DLRL and the specified undertaker are regulated by the provisions of Part III of the 1991 Act.

Acquisition of land

6.  DLRL shall not acquire any apparatus from a specified undertaker pursuant to this Order otherwise than by agreement.

7.  DLRL may in exercise of the powers of this Order acquire or appropriate any land in which any apparatus is placed and, following the removal of such apparatus in accordance with the provisions of this Schedule, any rights in that land relating to that apparatus shall be extinguished but no apparatus shall be removed nor shall any right of the specified undertaker to use, maintain, repair, renew or inspect any apparatus be extinguished until any necessary alternative apparatus has been constructed and is in operation to the reasonable satisfaction of the specified undertaker.

Removal of apparatus

8.  Paragraphs 9 to 11 apply where—

(a)DLRL requires the removal of any apparatus for the purpose of constructing any of the authorised works and gives to the specified undertaker not less than 56 days' written notice of that requirement together with a plan of the proposed work and of the proposed position of the alternative apparatus to be provided or constructed; or

(b)in consequence of the exercise or proposed exercise of any of the powers of this Order, the specified undertaker reasonably requires to remove any apparatus.

9.  DLRL shall, if it is practicable to do so, afford to the specified undertaker the necessary rights and facilities for the construction of any necessary alternative apparatus in other land which is available for the purpose and which is held or used, or intended for use, by DLRL for the purpose of its undertaking or in which it has sufficient rights or interests and thereafter for the use, maintenance, repair, renewal and inspection of such apparatus and, if DLRL is unable to obtain those rights and facilities, the specified undertaker shall, on receipt of a written notice to that effect from DLRL, use its best endeavours to obtain the necessary rights and facilities.

10.  Any alternative apparatus to be constructed by the specified undertaker pursuant to paragraph 9 shall be constructed in such manner, and in such line or situation, as may be agreed between the specified undertaker and DLRL or, in default of agreement, determined by arbitration.

11.  The specified undertaker shall, after the manner of construction and the line or situation of any necessary alternative apparatus have been agreed or determined and after the grant to or obtaining by the specified undertaker of any such facilities and rights as are referred to in paragraph 9, proceed with all reasonable despatch to construct and bring into operation the alternative apparatus and thereafter to remove any apparatus required by DLRL to be removed in accordance with paragraph 8.

Removal of apparatus and construction of alternative apparatus by DLRL

12.  Paragraphs 13 to 15 apply to so much of the work necessary in connection with the construction of alternative apparatus, or the removal of apparatus required to be removed, as will take place in any land held or used, or intended for use, by DLRL for the purpose of its undertaking.

13.  If DLRL gives notice in writing to the specified undertaker that it desires to carry out any part of any work to which this paragraph applies, such work, instead of being carried out by the specified undertaker, may be carried out by DLRL with the prior written consent of the specified undertaker (which shall not be unreasonably withheld and shall be subject to any such conditions as are reasonable and proper to protect the apparatus) in accordance with plans and in a position agreed between the specified undertaker and DLRL or, in default of agreement, determined by arbitration, with all reasonable despatch under the superintendence (if given) and to the reasonable satisfaction of the specified undertaker.

14.  In carrying out any work under paragraph 13 DLRL shall comply with all statutory obligations which would have been applicable had the works been carried out by the specified undertaker.

15.  Nothing in paragraph 13 shall authorise DLRL to carry out the actual placing, erection, installation, bedding, packing, removal, connection or disconnection of any apparatus or, where the apparatus is laid in a trench, execute any filling around the apparatus within 300 millimetres (measured in any direction) of the apparatus.

Facilities and rights for alternative apparatus

16.  Where, in accordance with the provisions of this Schedule, DLRL affords to the specified undertaker facilities and rights for the construction, use, maintenance, renewal and inspection in land of DLRL of alternative apparatus in substitution for apparatus to be removed as aforesaid, those facilities and rights shall be granted upon such terms and conditions as may be agreed between DLRL and the specified undertaker or, in default of agreement, determined by arbitration.

17.  In determining the terms and conditions mentioned in paragraph 16 in respect of alternative apparatus to be constructed across or along the authorised works the arbitrator shall—

(a)give effect to all reasonable requirements of DLRL for ensuring the safety of the authorised works and for securing any subsequent alterations or adaptations of the alternative apparatus which may be required to prevent interference with any such works; and

(b)so far as it may be reasonable and practicable to do so in the circumstances of the case, give effect to any terms and conditions applicable to the apparatus (if any) constructed across or along the authorised works for which the alternative apparatus is to be substituted and to any other reasonable requirements of the specified undertaker.

18.  If the facilities and rights to be afforded by DLRL in respect of any alternative apparatus under paragraph 16 and the terms and conditions subject to which the same are to be granted are, in the opinion of the arbitrator, more or less favourable on the whole to the specified undertaker than the facilities, rights, terms and conditions applying to the apparatus to be removed, the arbitrator shall make such provision for the payment of compensation to or by DLRL by or to the specified undertaker in respect thereof as shall appear to him to be reasonable having regard to all the circumstances of the case.

Retained apparatus: protection and plan approval

19.  Not less than 56 days before commencing to construct or renew any specified work, DLRL shall submit to the specified undertaker plans of the works.

20.  In relation to a work which is a specified work because of its proximity to or effect on a sewer, the plans to be submitted to the specified undertaker under paragraph 19 shall be detailed plans describing—

(a)the exact position of the specified work;

(b)the level at which it is proposed to be constructed or renewed;

(c)the manner of its construction or renewal;

(d)the position of all sewers within 15 metres of the specified work or upon which the specified work will impose a load; and

(e)by way of detailed drawings, every alteration proposed to be made to any such sewer.

21.  DLRL shall not commence the construction or renewal of any specified work to which paragraph 20 applies until the specified undertaker has given written approval of the plans so submitted.

22.  Any approval of the specified undertaker required under paragraph 21—

(a)may be given subject to reasonable conditions for any purpose mentioned in paragraph 23;

(b)shall not be unreasonably withheld; and

(c)shall be deemed to have been given if it is neither given nor refused within 56 days of the submission of plans for approval.

23.  In relation to a work to which paragraph 20 applies, the specified undertaker may require such modifications to be made to the plans as may be reasonably necessary for the purpose of securing its sewerage system against interference or risk of damage or for the purpose of providing or securing proper and convenient means of access to any sewer.

24.  A specified work shall be constructed (and in the case of any temporary work removed) only in accordance with—

(a)the plans submitted as aforesaid (and, in the case of plans relating to sewers approved, deemed to have been approved or settled by arbitration, as amended from time to time by agreement between DLRL and the specified undertaker); and

(b)all reasonable requirements made by the specified undertaker for the alteration, or otherwise for the protection, of the apparatus, or for securing access thereto;

and the specified undertaker shall be entitled by its officer to watch and inspect the carrying out of the work.

25.  If within 42 days after the submission to it of any plans under paragraph 19, in consequence of the works proposed by DLRL the specified undertaker reasonably requires the removal of any apparatus and gives written notice to DLRL of that requirement, the foregoing provisions of this Schedule shall have effect as if the removal of such apparatus had been required by the specified undertaker under paragraph 8.

26.  Nothing in paragraphs 19 or 25 shall preclude DLRL from submitting at any time, or from time to time, but in no case less than 28 days before commencing the construction of any specified work, a new plan thereof in lieu of the plan previously submitted, and thereupon the provisions of those paragraphs shall apply to, and in respect of, such new plan save that the reference in paragraph 25 to 42 days shall be treated as a reference to 21 days.

27.  DLRL shall not be required to comply with paragraph 19 in a case where it is necessary to carry out emergency works but, in such a case, it shall give to the specified undertaker notice so soon as reasonably practicable, and a plan of the works so soon as reasonably practicable thereafter, and shall comply with paragraph 24 so far as reasonably practicable in the circumstances.

28.  Nothing in paragraph 27 shall entitle DLRL to carry out works to any apparatus but, upon receipt of notice from DLRL, the specified undertaker shall proceed to carry out such works as may be required with all reasonable despatch.

Co-operation

29.  Where in consequence of the proposed construction of any of the authorised works, DLRL or a specified undertaker requires the removal of apparatus under paragraph 8 or a specified undertaker makes requirements for the protection or alteration of apparatus under paragraph 24, DLRL shall use its best endeavours to co-ordinate the execution of the works in the interests of safety and the efficient and economic execution of the authorised works and each specified undertaker shall use its best endeavours to co-operate with DLRL for that purpose.

Access

30.  If in consequence of the exercise of the powers of this Order the access to any apparatus is materially obstructed DLRL shall provide such alternative means of access to such apparatus as will enable the specified undertaker to maintain or use the apparatus no less effectively than was possible before such obstruction.

Expenses

31.  Subject to the provisions of the following paragraphs of this Schedule, DLRL shall repay to the specified undertaker the reasonable expenses incurred by the specified undertaker in, or in connection with—

(a)the inspection, removal and relaying or replacing, alteration or protection of any apparatus or the construction of any new apparatus under any provision of this Schedule (including any costs reasonably incurred or compensation properly paid in connection with the acquisition of rights or exercise of statutory powers for such apparatus);

(b)the cutting off of any apparatus from any other apparatus, or the making safe of any redundant apparatus in consequence of the exercise by DLRL of any power under this Order;

(c)the survey of any land, apparatus or works, the inspection and monitoring of works or the installation or removal of any temporary works reasonably necessary in consequence of the exercise by DLRL of any power under this Order; and

(d)any other work or thing rendered reasonably necessary in consequence of the exercise by DLRL of any such power;

within a reasonable time of being notified by the specified undertaker that it has incurred such expenses.

32.  There shall be deducted from any sum payable under paragraph 31 the value of any apparatus removed under the provisions of this Schedule, that value being calculated after removal.

33.  If in pursuance of the provisions of this Schedule—

(a)alternative apparatus of better type, or greater capacity or of greater dimensions is placed in substitution for existing apparatus of worse type, of smaller capacity or of smaller dimensions, except where this has been solely due to using the nearest currently available type; or

(b)apparatus (whether existing apparatus or alternative apparatus) is placed at a depth greater than the depth at which the existing apparatus was situated;

and the placing of apparatus of that type or capacity or of those dimensions, or the placing of apparatus at that depth, as the case may be, is not agreed by DLRL or, in default of agreement, is not determined by arbitration to be necessary having regard, among other things, to the nature of the authorised works, then, if such placing involves cost in the construction of works under paragraphs 9 to 11 exceeding that which would have been involved if the apparatus placed had been of the existing type, capacity or dimensions, or at the existing depth, as the case may be, the amount which apart from this paragraph would be payable to the specified undertaker by virtue of paragraph 31 shall be reduced by the amount of that excess.

34.  For the purposes of paragraph 33—

(a)an extension of apparatus to a length greater than the length of existing apparatus shall not be treated as a placing of apparatus of greater dimensions than those of the existing apparatus except in a case where the apparatus as so extended serves a purpose (either additional to or instead of that served by the existing apparatus) which was not served by the existing apparatus; and

(b)where the provision of a joint in a pipe or cable is agreed, or is determined to be necessary, the consequential provision of a jointing chamber or of a manhole shall be treated as if it also had been agreed or had been so determined.

35.  An amount which apart from this paragraph would be payable to the specified undertaker in respect of works by virtue of paragraphs 31 to 34 shall, if the works include the placing of apparatus provided in substitution for apparatus placed more than 7 years and 6 months earlier so as to confer on the specified undertaker any financial benefit by deferment of the time for renewal of the apparatus or of the system of which it forms part in the ordinary course, be reduced by the amount which represents that benefit as calculated in accordance with the Code of Practice entitled “Measures Necessary where Apparatus is Affected by Major Works (Diversionary Works)” and dated June 1992 and approved by the Secretary of State on 30th June 1992, as revised and re-issued from time to time.

36.  Paragraphs 31 to 35 shall not apply where the authorised works constitute major transport works for the purposes of Part III of the 1991 Act, but instead—

(a)the allowable costs of the construction of works under this Part of this Schedule shall be determined in accordance with section 85 of that Act (sharing the costs of necessary measures) and any regulations for the time being having effect under that section; and

(b)the allowable costs shall be borne by DLRL and the specified undertaker in such proportions as may be prescribed by any such regulations.

37.  In any case where work is carried out by DLRL pursuant to paragraphs 13 to 15 and, if such work had been carried out by the specified undertaker, the repayment made to the specified undertaker under paragraph 31 would fall to be reduced pursuant to paragraphs 33 to 35, the specified undertaker shall pay to DLRL such sum as represents the amount of that reduction.

Indemnity

38.  If by reason or in consequence of the construction, maintenance or failure of any of the authorised works, including any works carried out by DLRL pursuant to paragraph 13 or protective works required by a condition imposed under paragraph 22(a) or required under paragraph 24(b), or any subsidence resulting from any of those works, any damage shall be caused to any apparatus (other than apparatus the repair of which is not reasonably necessary in view of its intended removal for the purposes of those works) or other property of the specified undertaker, or there is any interruption in any service provided by the specified undertaker, DLRL shall repay the cost reasonably incurred by the specified undertaker in making good such damage, or restoring the supply, and shall—

(a)make reasonable compensation to the specified undertaker for any loss sustained by it; and

(b)indemnify the specified undertaker against all claims, demands, proceedings, costs, damages and expenses which may be made or taken against or recovered from, or incurred by, the specified undertaker;

by reason or in consequence of any such damage or interruption; and the fact that any act or thing may have been done by the specified undertaker on behalf of DLRL or in accordance with plans approved by the specified undertaker or in accordance with any requirement of the specified undertaker or under its supervision shall not, subject to paragraph 39, excuse DLRL from any liability under the provisions of this paragraph.

39.  Nothing in paragraph 38 shall impose any liability on DLRL with respect to any damage or interruption to the extent that such damage or interruption is attributable to the neglect or default of the specified undertaker, its officers, servants, contractors or other agents.

40.  The specified undertaker shall give to DLRL reasonable notice of any claim or demand as aforesaid and no settlement or compromise thereof shall be made without the prior consent of DLRL which shall not be unreasonably withheld.

Exercise of protective and survey powers

41.  DLRL shall, so far as is reasonably practicable, so exercise the powers conferred by article 20 of this Order as not to obstruct or render less convenient the access to any apparatus.

42.  DLRL shall not, in the exercise of the powers of section 11(3) of the 1965 Act, as applied by this Order, or of article 22 of this Order, make any trial holes which interfere with any apparatus without the consent of the specified undertaker (which shall not be unreasonably withheld).

Arbitration

43.  Any difference arising between DLRL and a specified undertaker under this Schedule (other than a difference as to its meaning or construction) shall be determined by arbitration in accordance with article 54 of this Order.

Transfer of powers

44.  DLRL shall give notice to every specified undertaker if any of the powers of DLRL under this Order are transferred to another person in accordance with article 46 of this Order and any such notice shall be given within 14 days of any such transfer becoming effective and shall describe or give (as appropriate)—

(a)the nature of the functions to be transferred;

(b)the extent of that transfer;

(c)the geographical area to which the transfer relates;

(d)the name and address of the transferee; and

(e)the effective date of the transfer.

45.  The obligation to give notice under paragraph 44 to a successor in title to a specified undertaker named in paragraph 1 shall only apply to the extent that DLRL has been informed by notice in writing by that named undertaker, or by a successor in title to that named undertaker, as the case may be, of the name and address of that successor in title.

Notices

46.  Any notice in writing to be given by DLRL to a specified undertaker under this Schedule shall be deemed effectively given if sent by recorded delivery or by registered letter addressed to the registered office of that specified undertaker.

Article 44

SCHEDULE 14FOR PROTECTION OF BRITISH WATERWAYS BOARD

1.—(1) For the protection of the Board the following provisions shall, unless otherwise agreed in writing between DLRL and the Board, have effect.

(2) In this Schedule—

“construction”, in relation to any specified work or protective work, includes—

(a)

the execution and placing of that work; and

(b)

any replacing, relaying, removal, alteration, renewal, maintenance, repair or reconstruction of that work as may be carried out during the period of 12 months from the completion of that work;

and “construct” and “constructed” have corresponding meanings;

“the designated areas” means those parts of the designated areas, as defined by section 2 of the 1994 Act, that were transferred to the Board by the London Docklands Development Corporation (Transfer of Functions) Order 1998(10);

“detriment” means any damage to a dock area or any other property of the Board and, without prejudice to the generality of that meaning, includes—

(a)

the erosion of the bed or banks of a dock area, or the impairment of the stability of any works, lands or premises forming part of a dock area;

(b)

the siltation of a dock area or the deposit of materials in it so as to permanently damage the dock area;

(c)

the pollution of a dock area;

(d)

any permanent alteration in the water level of a dock area, or permanent interference with the supply of water thereto, or drainage of water therefrom;

(e)

any permanent harm to the ecology of a dock area (including any permanent adverse impact on any site of special scientific interest comprised in the dock area);

“dock area” means the designated areas and includes the waterside and any works, lands or premises belonging to the Board, or under its management or control, and held or used by the Board in connection with the designated areas;

“the engineer” means an engineer appointed by the Board for the purpose in question;

“plans” includes sections, designs, drawings, specifications, soil reports, calculations, descriptions (including descriptions of methods of construction) and programmes;

“protective work” means a work constructed under sub-paragraph 8(3)(a);

“specified work” means so much of any of the authorised works as is situated upon, across, under, over or within 15 metres of, or may directly and physically affect the dock area;

“the waterside” means so much of the waterside as defined by section 2 of the 1994 Act, as is comprised within the foregoing definition of “the designated areas”.

2.  DLRL shall not under the powers conferred by this Order acquire compulsorily any land of the Board or any easement or other right over such land, other than such land or easements or other rights over such land, as is reasonably necessary for, or in connection with, the construction, maintenance or operation of the works authorised by this Order.

3.—(1) DLRL shall not in the exercise of the powers conferred by this Order permanently obstruct or interfere with pedestrian or vehicular access to a dock area unless such permanent obstruction or interference with such access is with the consent of the Board.

(2) Nothing in article 19 shall authorise DLRL—

(a)to discharge any water directly or indirectly into a dock area; or

(b)to carry out any works to, or make any opening in, or otherwise interfere with, a dock area (including the banks and bed thereof),

except with the consent of the Board and in accordance with plans approved by, and under the supervision (if given) of, the engineer.

(3) DLRL shall not exercise the powers conferred by article 20 in relation to any building forming part of a dock area, or situated on land or property of the Board forming part of a dock area, unless such exercise is with the consent of the Board.

(4) DLRL shall not exercise the powers conferred by article 22 or the powers conferred by section 11(3) of the 1965 Act, in relation to a dock area unless such exercise is with the consent of the Board.

(5) DLRL shall not exercise the powers conferred by sections 271 or 272 of the 1990 Act, as applied by Schedule 9 to this Order, so as to permanently divert any right of access to a dock area, but such right of access may be permanently diverted with the consent of the Board.

(6) The consent of the Board pursuant to any of sub-paragraphs (1), (3), (4) and (5) and the approval of plans under sub-paragraph (2) shall not be unreasonably withheld or delayed but may be given subject to reasonable conditions which in the case of article 19 may include conditions—

(a)specifying the maximum volume of water which may be discharged in any period; and

(b)authorising the Board on giving reasonable notice (except in an emergency, when the Board may require immediate suspension) to DLRL to require DLRL to suspend the discharge of water or reduce the flow thereof where this is necessary by reason of any operational requirement of the Board and where a reasonable alternative is available to enable DLRL to discharge the water in question during the period of the suspension.

4.  DLRL shall not use any land or property of the Board forming part of a dock area for the passage or siting of vehicles, plant or machinery employed in the construction of the specified work other than—

(a)with the consent in writing of the engineer whose consent shall not be unreasonably withheld; and

(b)subject to compliance with such reasonable requirements as the engineer may from time to time specify—

(i)for the prevention of detriment; or

(ii)in order to avoid or reduce any inconvenience to the Board, its officers and agents and all other persons lawfully on such land or property.

5.  If in consequence of or in connection with the exercise of the powers of this Order any part of a way over land forming part of a dock area or any public right of way giving access to a dock area (“the closed section”) is temporarily closed to persons on foot or on cycles and there is no way which provides a reasonable alternative, DLRL shall to the reasonable satisfaction of the Board, provide in substitution as sufficient and convenient way as is reasonably practicable between the points of commencement and termination of the closed section for such time as the closure continues.

6.  Where so required by the engineer DLRL shall to the reasonable satisfaction of the engineer fence off any specified work or protective work or take such other steps as the engineer may require to be taken for the purpose of separating a specified work or a protective work from a dock area, whether on a temporary or permanent basis or both.

7.—(1) Before the commencement of the initial construction of any part of the specified works and again following completion of the specified works DLRL shall bear the reasonable cost of the carrying out by a qualified engineer (“the engineer”) to be approved by the Board and DLRL of surveys (“the surveys”) of so much of the dock area and of any land and existing works of DLRL which may provide support for the dock area as will or may be affected by the specified works.

(2) For the purposes of the surveys DLRL shall—

(a)on being given reasonable notice (save in case of emergency, when immediate access shall be afforded) afford reasonable facilities to the engineer for access to the site of the specified works and to any land and existing works of DLRL which may provide support for the dock area as will or may be affected by the specified works; and

(b)supply the engineer as soon as reasonably practicable with all such information as he may reasonably require with regard to such existing works of DLRL and to the specified works or the method of construction thereof.

(3) The reasonable costs of the surveys shall include the costs of any dewatering or reduction of the water level of any part of the dock area (where reasonably required) which may be effected to facilitate the carrying out of the surveys and the provisions of this schedule shall apply with all necessary modifications to any such dewatering or reduction in the water level as though the same were specified works.

(4) Copies of the surveys shall be provided to both the Board and DLRL.

8.—(1) DLRL shall before commencing construction of any specified work including any temporary works supply to the Board proper and sufficient plans of that work and such further particulars available to it as the Board may within 14 days of the submission of the plans reasonably require for the approval of the engineer and shall not commence such construction of any specified work until plans of that work have been approved in writing by the engineer or settled by arbitration.

(2) The approval of the engineer under sub-paragraph (1) shall not be unreasonably withheld or delayed, and if within 56 days after such plans (including any other particulars reasonably required under sub-paragraph (1)) have been supplied to the Board the engineer has not intimated his disapproval of those plans and the grounds of his disapproval he shall be deemed to have approved the plans as submitted.

(3) When signifying his approval of the plans the engineer may specify—

(a)any protective work (whether temporary or permanent) which is reasonably necessary to be carried out before the commencement of any specified work to prevent detriment; and

(b)such other requirements as may be reasonably necessary to prevent detriment;

and such protective work shall be constructed by the Board or (if the Board so desires) by DLRL with all reasonable dispatch and DLRL shall not commence the construction of any specified work until the engineer has notified DLRL that the protective work has been completed to his reasonable satisfaction.

9.  Without prejudice to its obligations under the foregoing provisions of this Schedule DLRL shall consult the Board on—

(a)the design and appearance of the specified works, including the materials to be used for their construction; and

(b)the environmental effects of the specified works;

and shall have regard to such views as may be expressed by the Board, to the extent that these accord with the requirements of the local planning authority in response to such consultation pursuant, in particular, to the requirements imposed on the Board by section 22 (General environmental and recreational duties) of the British Waterways Act 1995(11) and to the interest of the Board in preserving and enhancing the environment of dock areas.

10.  DLRL shall give to the engineer 56 days' notice of its intention to commence the construction of any of the specified or protective works, or, in the case of repair carried out in an emergency, such notice as may be reasonably practicable so that, in particular, the Board may where appropriate arrange for the publication of notices bringing those works to the attention of users of a dock area.

11.  DLRL shall provide and maintain at its own expense in the vicinity of any specified or protective work such temporary lighting and such signal lights for the control of navigation as the engineer may reasonably require during the construction or failure of the specified or protective work.

12.—(1) Any specified works shall, when commenced, be constructed—

(a)with all reasonable dispatch in accordance with the plans approved or deemed to have been approved or settled as aforesaid and with any requirements made under paragraph 8(3)(a);

(b)under the supervision (if given) and, in the case of any specified work which directly and physically affects a dock area, to the reasonable satisfaction of the engineer;

(c)in such manner as to cause as little detriment as is reasonably practicable;

(d)in such manner as to cause as little inconvenience as is reasonably practicable to the Board, its officers and agents and all other persons lawfully using a dock area.

(2) Nothing in this Order shall authorise DLRL to make or maintain any permanent works in or over a dock area so as to impede or prevent (whether by reducing the headroom or depth of water available for vessels, or the width of a dock area or otherwise) the passage of any vessel such as would have been capable of navigating a dock area on 29th June 2004.

(3) Following the completion of the construction of the specified work DLRL shall restore a dock area to a condition no less satisfactory than its condition immediately prior to the commencement of that work.

13.—(1) Any pile, stump or other obstruction which becomes exposed in consequence of a specified work shall be removed by DLRL or, if it is not reasonably practicable to remove it, shall be cut off at such level below the bed of a dock area as the Board may direct.

(2) If DLRL fail to remove any such pile, stump or other obstruction within 28 days after receipt of written notice from the Board requiring the removal, the Board may carry out the removal and recover its costs from DLRL.

14.  DLRL shall not in the course of constructing any specified work or protective work or otherwise in connection therewith do or permit anything which may result in the pollution of a dock area or the deposit of materials therein and shall take such steps as the engineer may reasonably require to avoid or make good any breach of its obligations under this paragraph; but this provision shall not prevent DLRL from carrying out works within a dock area.

15.—(1) DLRL shall at all times on being given reasonable notice allow reasonable facilities to the engineer for access to any specified work during its construction; but such facilities for access shall be subject to DLRL’s reasonable requirements for ensuring the safety of the railway and of the engineer and other persons working on the railway.

(2) DLRL shall supply the engineer with all such information as he may reasonably require with regard to any specified work or the method of constructing it.

16.—(1) If during the construction of a specified work or during a period of 24 months after the completion of a specified work any alterations or additions, either permanent or temporary, to a dock area are reasonably necessary in consequence of the construction of the specified work in order to avoid detriment, and the Board gives to DLRL reasonable notice of its intention to carry out such alterations or additions (which shall be specified in the notice), DLRL shall pay to the Board the reasonable cost of those alterations or additions including, in respect of any such alterations and additions as are to be permanent, a capitalised sum representing the increase of the costs which may be expected to be reasonably incurred by the Board in maintaining, working and, when necessary, renewing any such alterations or additions.

(2) If the cost of maintaining, working or renewing a dock area is reduced in consequence of any such alterations or additions a capitalised sum representing such saving shall be set off against any sum payable by DLRL to the Board under this paragraph.

17.—(1) DLRL shall upon completion of any part of any permanent specified work remove as soon as practicable any temporary works and materials for temporary works constructed or placed in, on, over or under a dock area in connection with that part of the work.

(2) All temporary works shall be removed to the reasonable satisfaction of the engineer; and in the construction, maintenance and removal of such works DLRL shall not cause unavoidable detriment.

18.  If at any time after the completion of a specified work, not being a work vested in the Board, the Board gives notice to DLRL informing it that the state of maintenance of the work appears to be such that the work is causing or likely to cause detriment, DLRL shall, on receipt of such notice, take such steps as may be reasonably necessary to put the work in such state of maintenance as not to cause such detriment.

19.  Any additional expenses which the Board may reasonably incur in altering, reconstructing or maintaining a dock area under any powers existing at the making of this Order by reason of the existence of a specified work shall, provided that 56 days' previous notice of the commencement of such alteration, reconstruction or maintenance has been given to DLRL, be repaid by DLRL to the Board.

20.  DLRL shall repay to the Board all fees, costs, charges and expenses reasonably incurred by the Board—

(a)in constructing any protective works under the provisions of paragraph 8(3)(a) including, in respect of any permanent protective works, a capitalised sum representing the cost of maintaining and renewing those works;

(b)in respect of the approval by the engineer of plans submitted by DLRL and the supervision by him of the construction or repair of any specified work and any protective work;

(c)in respect of the employment during the period of the initial construction of any specified work or protective work of any inspectors, watchmen and other persons whom it shall be reasonably necessary to appoint for inspecting, watching and lighting any dock area and for preventing, so far as may be reasonably practicable, interference, obstruction, danger or accident arising from the construction or failure of the specified work or any protective work; and

(d)in bringing the specified work or any protective work to the notice of users of a dock area.

21.—(1) If any detriment shall be caused by the construction or failure of the specified work or the protective works, DLRL (if so required by the Board) shall make good such detriment and shall pay to the Board all reasonable expenses to which the Board may be put, and compensation for any loss which the Board may sustain, in making good or otherwise by reason of the detriment.

(2) DLRL shall be responsible for and make good to the Board all costs, charges, damages, expenses and losses not otherwise provided for in this Schedule which may be occasioned to or reasonably incurred by the Board—

(a)by reason of the construction of any specified work or a protective work or the failure thereof; or

(b)by reason of any act or omission of DLRL or of any person in its employ or of its contractors or others whilst engaged upon the construction of any specified work or of a protective work;

and subject to sub-paragraph (4) DLRL shall effectively indemnify and hold harmless the Board from and against all claims and demands arising out of any of the matters referred to in paragraphs (a) and (b).

(3) The fact that any act or thing may have been done by the Board on behalf of DLRL or in accordance with plans approved by the engineer or in accordance with any requirement of the engineer or under his supervision or in accordance with any directions or awards of an arbitrator shall not (if it was done without negligence on the part of the Board or of any person in its employ or of its contractors or agents) excuse DLRL from any liability under the provisions of this paragraph.

(4) The Board shall give DLRL reasonable notice of any such claim or demand as aforesaid and no settlement or compromise of such a claim or demand shall be made without the prior consent of DLRL.

22.  Where under any provision of this Schedule the Board or DLRL (as the case may be) is entitled to a capitalised sum, it shall provide such details of the formula by which the sum is calculated as may reasonably be requested by the party required to pay the sum.

23.  Except as provided by this Order, nothing in this Order shall prejudice or derogate from the estates, rights, interests, privileges, liberties or franchises of the Board or alter or diminish any power, authority or jurisdiction vested in the Board at the commencement of this Order.

24.  Any difference arising between DLRL and the Board under this Schedule (other than a difference as to the meaning or construction of this Schedule) shall be referred to and settled by arbitration in accordance with article 54.

Article 45

SCHEDULE 15TRAFFIC REGULATION

(1)(2)
AreaStreet
The London borough of Tower Hamlets

Back Church Lane

Pinchin Street

Stepney Causeway

The London borough of GreenwichConington Road
The London borough of LewishamConington Road

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources