95.—(1) Without prejudice to the other provisions of this Part of this Schedule, before commencing the construction or renewal of any specified work, and in the case of any specified work of a temporary nature its removal, the undertaker shall submit to the company plans as described in sub-paragraph (2) (“the plans”) and shall not commence that work until the company has signified in writing its approval of those plans.

(2) The plans to be submitted to the company shall be detailed plans, drawings, sections and specifications describing the position and manner in which, and the level at which, any specified work is proposed to be constructed and the position of all apparatus within 15 metres of that work (or 200 metres where explosives are to be used) or upon which the specified work will impose a load and shall include detailed drawings of any works for alteration or replacement or protection of such apparatus which the undertaker may propose.

(3) For the purpose of the preparation of the plans and subject to such reasonable requirements as it may specify, the company shall promptly upon the undertaker’s reasonable request permit the undertaker to have access to plans in its possession and to any of its apparatus.

(4) Any approval of the company required under this paragraph—

(a)may be given subject to reasonable conditions;

(b)shall not be unreasonably withheld; and

(c)shall be deemed to have been given if it is neither given nor refused within 42 days of the submission of plans for approval.

(5) Prior to their approval under sub-paragraph (1), the company may require such modifications to be made to the plans as may be reasonably necessary for the alteration or replacement of apparatus, to secure apparatus and the remainder of its undertaking as a sewerage undertaker and water undertaker against interference or risk of damage and to provide and secure reasonably proper and convenient means of access to apparatus and its sewage treatment works.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources