4.—(1) Subject to the provisions of any contract, any claim for payment for work carried out under the provisions of the 1988 Act shall be submitted so as to be received by the Commission no later than five months after the completion of the work for which payment is claimed.
(2) Subject to sub-paragraph (3), the Commission may refuse any claim for payment mentioned in sub-paragraph (1) which is received late without good reason.
(3) No claim for payment shall be refused unless the solicitor has been given a reasonable opportunity to show why it should not be refused.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: