- Latest available (Revised)
- Original (As made)
This is the original version (as it was originally made). UK Statutory Instruments are not carried in their revised form on this site.
Statutory Instruments
OFFSHORE INSTALLATIONS
Made
11th July 2001
Coming into force
1st August 2001
The Secretary of State, in exercise of the powers conferred on him by section 22(1) and (2) of the Petroleum Act 1987(1) (hereinafter referred to as “the Act”) and of all powers enabling him in that behalf, hereby makes the following order:
1. This order may be cited as the Offshore Installations (Safety Zones) (No. 2) Order 2001 and shall come into force on 1st August 2001.
2. A safety zone is hereby established around each installation specified in column 1 of the Schedule hereto (being an installation stationed in waters to which subsection (7) of section 21 of the Act applies) having a radius of five hundred metres from the point as respects that installation which has the co-ordinates of latitude and longitude according to European Datum (1950) specified in columns 2 and 3 of the Schedule.
Signed by authority of the Secretary of State
Alan Whitehead
Parliamentary Under Secretary of State,
Department for Transport, Local Government and the Regions
11th July 2001
Article 2
| (1) | (2) | (3) |
|---|---|---|
| Name or other designation of the offshore installation | Latitude North | Longitude |
| South Everest Subsea Installation | 57°41'22.511" | 01°45'27.727"E |
| Pipe Line End Manifold, Magnus EOR Development | 60°16'56.2" | 03°48'21.1"W |
| Clair Tee, Magnus EOR Development | 60°36'45" | 02°27'19.1"W |
| Nevis Facility Lewis 1 Well | 59°31'18.13" | 01°25'25.25"E |
| Hamilton East Wellhead | 53°36'03" | 03°25'05.92"W |
| North Leadon Cluster “A” | 59°34'51.45" | 01°39'19.33"E |
| FPSO at Mid-Line Structure | 59°33'43.05" | 01°39'29.53"E |
| South Leadon Cluster “B” | 59°32'33.76" | 01°39'29.6"E |
| Angus Well | 56°09'22.9" | 03°03'32.24"E |
| East Telford Well | 58°12'31.32" | 0°18'32.298"E |
(This note is not part of the order)
This order establishes, under section 22 of the Petroleum Act 1987, safety zones having a radius of 500 metres from the specified point, around each installation specified in the Schedule to this order and stationed in waters to which section 21(7) of that Act applies (these include territorial waters and waters in areas designated under section 1(7) of the Continental Shelf Act 1964 (c. 29)) (article 2).
Vessels, which for this purpose include hovercraft, submersible apparatus and installations in transit, are prohibited from entering or remaining in a safety zone except with the consent of the Health and Safety Executive or in accordance with regulations made under section 23(1) of the Act (currently the Offshore Installations (Safety Zones) Regulations 1987/1331).
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made):The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: