SCHEDULETHE SCHEME FOR CONSTRUCTION CONTRACTS

PART II—PAYMENT

Dates for payment6

Payment of the contract price under a construction contract (not being a relevant construction contract) shall become due on

a

the expiry of 30 days following the completion of the work, or

b

the making of a claim by the payee,