PART IIWORKS

Power to construct works

3.  Subject to the provisions of this Order the Authority may in the lines and situations and within the limits of deviation shown on the deposited plans and according to the levels shown on the deposited sections, construct, execute and maintain the works hereinafter described, with all necessary works and conveniences connected therewith, in the parish of Glenelg within the Lochaber district and the Highland Region—

  • Work No.1

    Refacing of the existing marshalling area on its eastern side in reinforced concrete or steel sheet piling with infilling and levelling behind, commencing at a point NM6765897188, 98 metres north-north-east of the northern extremity of the Authority’s office and extending in a north-north-westerly direction for a distance of 30 metres to a point at NM6764997217 and there terminating.

  • Work No. 2

    The construction of a sea wall and the reclamation of the seabed and foreshore behind by infilling, levelling and surfacing an area of irregular shape comprising of 0.75 hectares, commencing at the termination of Work No. 1 and extending in a west-north-westerly direction for a distance of 134 metres to a point at NM6723397262 and there terminating.

  • Work No. 3

    A slipway of solid construction at a point at NM6758297256, 76.7 metres north-west of the commencement of Work No. 2 and extending in an east-north-easterly direction for a distance of 125 metres to a point at NM6770197295 and there terminating.

  • Work No. 4

    A breakwater of solid construction bounded on all sides by rock facing commencing at a point at NM6756997295, 40 metres north-north-west of the commencement of Work No. 3 and extending in an east-north-easterly direction for a distance of 113 metres to a point at NM6767697329 and there terminating.

  • Work No. 5

    A breakwater of solid construction commencing at a point at NM6767897326, 4.5 metres south-south-east of the termination of Work No. 4 and extending in an east-north-easterly direction for a distance of 107 metres to a point at NM6778097358, thence in a south-south-easterly direction for a distance of 65 metres to a point at NM6780097298 and there terminating.

  • Work No. 6

    A deepening by means of excavation within the area marked “Limit of dredged area (Work No. 6)” on the deposited plans to a depth of 7 metres below the level of low water commencing at point A and extending in a west-south-westerly direction for a distance of 175.5 metres to point B, thence in a south-south-easterly direction for a distance of 113 metres to point C, thence in an east-north-easterly direction for a distance of 216 metres to point D, thence in a northerly direction for a distance of 99.5 metres to point E, thence in a north-north-westerly direction for a distance of 95 metres to point F, thence in a westerly direction for a distance of 43 metres to point G, and thence in a southerly direction for a distance of 96 metres to the point of commencement.

  • Work No. 7

    A breakwater of solid construction commencing at a point at NM6778297233, 141 metres east-north-east of the commencement of Work No. 1 and extending in a north-north-westerly direction for a distance of 40 metres to a point at NM6778097270 and there terminating.

Power to renew, etc., works

4.  Subject to the provisions of this Order, the Authority may, within the limits of deviation, renew, replace, or otherwise alter temporarily or permanently the works.

Power to deviate

5.  Subject to the provisions of this Order, in the construction or execution of Works numbered 1 to 5 and 7 authorised by article 3 above, the Authority may deviate laterally from the lines or situations thereof shown on the deposited plans to the extent of the limits of deviation and may deviate vertically from the levels of those works shown on the deposited sections to any extent not exceeding 2 metres upwards and to any extent downwards as may be found necessary or convenient.

Subsidiary works

6.  Subject to the provisions of this Order the Authority for the purposes of or in connection with the works may within the limits of deviation construct, execute and maintain all such subsidiary or incidental works and conveniences as may be necessary or expedient for or in connection with those works.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made):The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once