This Order authorises the Mallaig Harbour Authority to construct a new fishery harbour by means of reclamation and infilling and the construction of a new breakwater and slipway. It also authorises dredging in connection with the proposed works.
The applicant for this Order is the Mallaig Harbour Authority, Harbour Offices, Mallaig, PH41 4QB.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made):The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.