The Portsmouth (Camber Dock) Harbour Revision Order 1995

Power to construct works

4.—(1) Subject to the provisions of this Order, the Council may, when they have acquired the necessary lands or obtained sufficient interests therein, make and maintain within the limits of deviation, the following works in the City of Portsmouth—

  • A quay wall on the seaward side of the existing Town Quay Inner Camber Berths 5 to 10 commencing by a junction at the southern end of Berth 5 at a distance of 3 metres from the existing seaward face extending parallel to that face in a northerly direction for 61 metres, then turning easterly and 3 metres off and parallel to the existing seaward face of Berth 6 for a distance of 91 metres, then turning south-easterly 3.5 metres off and parallel to the existing seaward face of Berth 7 for a distance of 55 metres, then turning south-south-easterly 3 metres off and following the existing curved seaward face of Berth 8 for a distance of 69 metres, then turning west-south-westerly 2.5 metres off and parallel to the existing seaward face of Berths 9 and 10 for a distance of 112 metres terminating by a junction with the existing quay face of Lucas Quay.

(2) The Council may within the limits of deviation extend, enlarge, alter, replace or relay the authorised works.

(3) The Council may authorise any person to carry out the authorised works.