(This note is not part of the Regulations)
These Regulations make provision for the sharing of costs between the highway, bridge or transport authority (“the authority”) and the undertaker where the undertaker’s apparatus in a street is affected by major highway, bridge or transport works (“the works”) and measures are required to protect it.
Where the works are initiated by the authority and the measures necessary to protect the apparatus are taken by the undertaker the authority shall pay to the undertaker the whole of his allowable costs (as defined in regulation 2(2)), but only 82 per cent of this sum shall be payable if 75 per cent of the estimate of 82 per cent of the allowable costs is paid as a lump sum before the works begin or, in the case of works lasting longer than 3 months, by instalments during the carrying out of the works: regulation 3 and 9(a). Where the works are initiated by the authority and the authority also takes the measures needed to protect the undertaker’s apparatus, the undertaker shall pay 18 per cent of the allowable costs: regulation 4. Where the undertaker requests the authority to move his apparatus solely because of a change in the type of highway construction, he is liable to pay the whole of the allowable costs: regulation 5. In the case of works inititated by a person other than an authority in its capacity as such or an undertaker the foregoing rules apply to protective measures depending on whether they are taken by the authority or the undertaker, but allowance must be made in full for any contribution agreed to be made towards the cost of those measures: regulation 6.
An undertaker is not liable for costs in relation to providing space in or strengthening of a bridge to accommodate his apparatus (regulation 7(1)) and cannot recover costs where he has placed his apparatus in the street after the authority has given him statutory notice of his intention to carry out works (regulation 7(2)). Provision is made requiring the undertaker to give credit for any gain received by him from betterment of his apparatus or deferment of the need to renew his apparatus resulting from protective measures taken (regulation 8). Further provision is made as to the timing and manner of payment (regulation 9(b)) and exclusions (regulation 10).
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made):The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.