THE SCHEDULETHE COUNTY COUNCIL OF SOMERSET (BRIDGWATER BYPASS) (NORTH) (RIVER PARRETT BRIDGE) SCHEME 1988

The Somerset County Council (hereinafter referred to as “the Council” makes this Scheme in exercise of their powers under Section 106(3) of the Highways Act 1980and of all other enabling powers:–

1.  The Council are authorised to construct over the navigable waters of the River Parrett the bridge specified in Schedule 1 to the Scheme as part of the highway which they are proposing to construct from a point 30 metres east of the Bridgwater–Cannington County Road (A39) (Main Road) in a generally easterly direction to its junction with Bristol Road (A38) 945 metres south of the roundabout at Dunball at Bridgwater in the District of Sedgemoor in the County of Somerset, and the provisions contained in Schedule 2 to the Scheme shall apply for the purpose of regulating its operation.

2.  This Scheme may be cited as the County Council of Somerset (Bridgwater Bypass) (North) (River Parrett Bridge) Scheme 1988.

SCHEDULE 1SPECIFICATION OF THE RIVER PARRETT BRIDGE

Plans

1.  Location Plan.

2.  Site Plan

3.  Elevation from the South.

The proposed bridge will be a five span structure, comprising three fixed approach spans to the east, an opening span comprising an overhead counter weight bascule located over the deep water channel adjacent to the west flood bank, and a further fixed span to the west. The fixed approach spans will be each approximately 25 metres and the bascule span will provide a clear navigation width of 9 metres.

The overall bridge length will be approximately 130 metres. The bridge will carry a single carriageway of 7.300 metres with a 2.000 metre footway on each side.

The overall width of the superstructure will be generally 12.300 metres and the soffit level will be 8.500 metres A.O.D.

The approach spans will be of composite construction, comprising steel plate girders acting compositely with a reinforced concrete deck. The three approach spans on the east side will be continuous over the intermediate piers, while the west span will be simply supported.

The bascule span will be pivoted on the main pier sited on the west side of the navigation channel and will comprise a trough stiffened steel orthotropic deck, surfaced with bauxite chippings in epoxy resin. The counterweight frame and towers will be of stiffened steel box construction.

The lifting span will be raised and lowered by hydraulic cylinders acting on a steel torsion box at the rear of the lifting leaf. The cylinders will be driven by hydraulic pumps and motors housed in a separate machinery room sited behind the west flood bank.

Each abutment will comprise a reinforced concrete bank seat supported on piled foundations. Each intermediate pier will comprise a reinforced concrete crosshead and reinforced concrete columns supported on a piled base slab. The main and nose piers will be reinforced concrete structures supported on groups of piles.

The main pier will be a two level structure, with the hydraulic cylinders being housed below road level.

Fendering will be provided to the main and nose piers, and mooring facilities will be provided approximately 100 metres upstream and downstream of the bridge.

Concrete mattress protection will be provided to the flood banks in the vicinity of the bridge.

SCHEDULE 2PROVISIONS FOR REGULATING THE OPERATION OF THE BRIDGE

The bridge will be open free of charge for the passage of vessels for such reasonable periods as may be required on every day between the hours of sunrise or 0600 hours (whichever is the later) and sunset or 2200 hours (whichever is the earlier) and at all other times the bridge will be closed against vessels except in case of emergency or after prior arrangement with the bridge operator.

Given under the Common Seal of the Council the twelfth day of December, One thousand nine hundred and eighty-eight.

The Common Seal of the Council was hereunto affixed in the presence of:–

L.S.

Senior Assistant Solicitor

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made):The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources