PART IIDESCRIPTION OF PIPE-LINES

(1)(2)(3)(4)
Route of pipe-linesNominal diameter in inchesDate brought into use
FromTo
Beryl B PlatformBeryl A Platform206.7.84
Beryl A PlatformBeryl SPM 23231.10.88
Beryl A PlatformBeryl SPM 33231.10.87
Beryl B PlatformSubsea W. I. Well Ness 9/13–31Z616.3.87
Beryl B PlatformNess subsea Gas Lift Manifold624.9.87
Beryl B PlatformSubsea W. I. Well Beryl 9/13–32 (PP)61.11.87
Beryl B PlatformSubsea W. I. Well 9/13–34 (PU)617.7.88
Beryl B PlatformSubsea Well Beryl 9/13–30 (PV)630.11.87
Subsea Production Well Ness 9/13 – 28ABeryl B Platform611.8.87
Subsea Production Well Ness 9/13 – 38z (CA) (formally numered 9/13 – 31Z)Beryl B Platform623.2.88

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made):The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once