xmlns:atom="http://www.w3.org/2005/Atom"

SCHEDULES

FIFTH SCHEDULEProvisions as to certain drainage schemes

1Every scheme shall set out—

(a)the area of the land to be drained in pursuance of the scheme;

(b)a description of the works proposed to be executed in pursuance of the scheme;

(c)the estimated cost of preparing and carrying out the scheme;

(d)the amount of any grant which will, if the scheme is approved by the Minister, be made by him to the Catchment Board by whom the scheme was prepared (hereafter in this Schedule referred to as " the Board") towards the expenditure incurred by the Board in preparing and carrying out the scheme; and

(e)the basis of apportionment, as between the lands comprised in the area of the scheme, of the net cost of the scheme.