(1)Part 5 of F(No.2)A 2023 (electricity generator levy) is amended as follows.
(2)In section 280 (key concepts), in subsection (1), in the definition of “relevant” (as in relevant generating station)—
(a)omit the “and” after paragraph (a), and
(b)after paragraph (b) insert “, and
(c)to the extent it is not comprised of qualifying new generating plant (see section 311A);”.
(3)After section 311 insert—
(1)Generating plant is “qualifying new generating plant” if it is new generating plant commissioned as part of a qualifying project that meets the new investment condition.
(2)The new investment condition is met in relation to a qualifying project if on 21 November 2023 it was reasonable to conclude, having regard to all of the circumstances, that there is a significant likelihood of the project not proceeding.
(3)The Treasury may by regulations provide for cases in which qualifying projects are to be treated as meeting the new investment condition.
(4)“Qualifying project” means a project to commission—
(a)new generating plant for—
(i)a new generating station, or
(ii)an existing generating station which (as a result of the project) is to be wholly or substantially comprised of new generating plant, or
(b)new generating plant that increases the generating capacity of an existing generating station.
(5)Subsection (6) applies where new generating plant that increases the generating capacity of an existing generating station replaces existing generating plant.
(6)Only so much of the new generating plant as represents generating capacity in excess of the capacity of the generating plant it replaces is to be regarded as qualifying new generating plant.”
(4)In section 313 (definitions in this Part), in the table, at the appropriate place insert—
“qualifying new generating plant | section 311A”. |
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: