SCHEDULES
PART 3 Construction and maintenance of highways
13.(1) Sub-paragraph (2) applies where under this Act the nominated...
14.(1) Where under this Act the nominated undertaker is authorised...
15.(1) This paragraph applies in relation to a work authorised...
18.Where the nominated undertaker is responsible for maintaining a bridge...
19.Section 58(1) and (2) of the Highways Act 1980 (special...
20.Notwithstanding anything in section 46 of the Railways Clauses Consolidation...
Acquisition of land: application of compulsory purchase legislation
Acquisition of rights in land etc: application of compulsory purchase legislation
Acquisition of rights in land: substituted Schedule 2A for Compulsory Purchase Act 1965
Land where powers of acquisition are limited to sub-surface acquisition
Highways: restrictions on powers to use subsoil and acquire land
Temporary possession and use of land
Conditions of deemed planning permission
7.Conditions relating to waste and spoil disposal and excavation
8.(1) If the relevant planning authority is a qualifying authority,...
9.Conditions on bringing scheduled works and depots into use
10.Where the relevant planning authority approves a scheme for the...
11.Condition relating to discontinuation of ancillary operations
1.Traffic authority to consult Secretary of State before making traffic regulation order
4.Power of Secretary of State to direct traffic authority to make traffic regulation order
5.(1) This paragraph applies where, in pursuance of a direction...
6.(1) This paragraph applies where, in pursuance of a direction...
7.Further powers of Secretary of State (including in relation to variation or revocation of orders)
10.(1) This paragraph applies to an order under paragraph 8...
11.Power to restrict traffic authority from making or implementing traffic regulation order
12.Consultation requirements applicable to Secretary of State
1.(1) The following provisions of this Part have effect, unless...
2.Wherever in this Part provision is made with respect to...
3.In exercising the powers conferred by this Act in relation...
4.(1) This paragraph applies to the construction of any tunnel,...
6.(1) The provisions of this paragraph have effect in relation...
7.The nominated undertaker must— (a) secure that so much of...
8.(1) Any officer of the highway authority duly appointed for...
9.(1) The nominated undertaker must not alter, disturb or in...
10.The nominated undertaker must not remove any soil or material...
11.(1) If the highway authority, after giving to the nominated...
12.The nominated undertaker must not, except with the consent of...
13.The nominated undertaker must, if reasonably so required by the...
15.(1) This paragraph applies where damage to any highway or...
17.(1) Any dispute arising between the nominated undertaker and the...
PART 2 Electricity, gas, water and sewerage undertakers
18.(1) The following provisions of this Part have effect, unless...
19.(1) The following provisions of this paragraph have effect in...
20.(1) This paragraph applies where— (a) the nominated undertaker for...
21.(1) Any alternative apparatus to be constructed by the undertakers...
22.(1) This paragraph applies where— (a) the manner of construction...
23.(1) This paragraph applies where the nominated undertaker gives notice...
24.(1) This paragraph applies where, in accordance with the provisions...
25.(1) Not less than 28 days before commencing to construct...
28.(1) Subject to the following provisions of this paragraph, the...
29.(1) This paragraph applies where, by reason of the construction...
30.In any case where Network Rail Infrastructure Limited (“Network Rail”)...
31.(1) Any dispute arising between the nominated undertaker and the...
PART 3 Electronic communications code networks
32.(1) The following provisions of this Part have effect, unless...
33.(1) Subject to sub-paragraph (2), Part 10 of the electronic...
34.The temporary stopping up or diversion of any highway under...
36.(1) Where the nominated undertaker or the Secretary of State...
37.(1) Sub-paragraph (2) applies where, by reason of the construction...
38.In any case where Network Rail Infrastructure Limited (“Network Rail”)...
39.(1) Any dispute arising between the nominated undertaker and an...
PART 4 Land drainage, flood defence, water resources and fisheries
40.(1) The following provisions of this Part have effect, unless...
41.(1) Before beginning to construct any specified work, the nominated...
42.(1) This paragraph applies to any request for approval of...
43.The requirements which the drainage authority may make under paragraph...
44.(1) Any specified work, and all protective works required by...
45.(1) Subject to sub-paragraph (5) the nominated undertaker must from...
47.(1) The nominated undertaker must take all such measures as...
48.(1) The nominated undertaker must indemnify the drainage authority from...
49.Nothing in paragraph 48 requires the nominated undertaker to indemnify...
51.Any dispute arising between the nominated undertaker and the drainage...
52.(1) The following provisions of this Part have effect, unless...
53.The Secretary of State must not under the powers under...
54.(1) Before beginning to construct any specified work, the nominated...
55.(1) Any specified work, and any protective works required by...
56.(1) The nominated undertaker must not deposit any polluting material...
60.(1) The nominated undertaker must indemnify Canal & River Trust...
61.(1) Nothing in paragraph 60 is to impose any liability...
62.(1) Any dispute arising between the nominated undertaker and Canal...
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: