High Speed Rail (London - West Midlands) Act 2017

This section has no associated Explanatory Notes

21(1)A planning authority may at the request of the nominated undertaker make a non-material change to any approval given under Part 1 of this Schedule.U.K.

(2)In deciding whether a change is material, a planning authority must have regard to the effect of the change, together with any previous changes made under this paragraph, on the approval as originally given.

(3)The power under sub-paragraph (1) includes power to impose new conditions or to alter or remove existing conditions.

(4)The approval as changed must represent an approval the authority could have given originally.

(5)The consultation requirements in this Part of this Schedule do not apply to a change under this paragraph.