Part 8U.K.Oil activities

Chapter 5U.K.Ring fence expenditure supplement

Post-commencement supplementU.K.

325The pool of ring fence losses and the pool of non-qualifying Schedule 19B lossesU.K.

(1)For the purpose of determining the amount of any post-commencement supplement, a qualifying company is to be taken at all times in its post-commencement periods to have a continuing mixed pool (the “ring fence pool”) of—

(a)the carried forward qualifying Schedule 19B amount (if any),

(b)the company's ring fence losses, and

(c)post-commencement supplement.

(2)The ring fence pool continues even if the amount in it is nil.

(3)For the purpose of determining the amount of any post-commencement supplement, a qualifying company is also to be taken in its post-commencement periods to have a non-qualifying pool consisting of the carried forward non-qualifying Schedule 19B amount.

(4)But the non-qualifying pool ceases to exist when the amount in it is reduced to nil.

(5)In this section—