543.New developments such as retail parks or housing projects require connections to the local electricity distribution network. When assessing the capital costs of such developments, developers need to know how much such a connection would cost and can request a network connection offer from the relevant Distribution Network Operator. The Distribution Network Operator is required, under the Electricity Act 1989, to provide a network connection offer following such a request. When providing the connection offer, the Distribution Network Operator will incur costs, for example, in determining the most appropriate point of connection to its network, designing the connection to the network and assessing what upstream changes need to be made to provide the load requested.

544.Until 2008, the practice was that Distribution Network Operators charged persons making connection requests up front for the costs incurred when providing network connection offers(7). However, following a complaint lodged with the Authority about this practice, legal advice confirmed that the Electricity Act 1989 only permitted Distribution Network Operators to recover these costs if an actual connection to the network was made. Since this issue came to light, the Authority has required Distribution Network Operators to change their charging methodologies to remove all elements of up front charging and bring them in line with the statutory arrangements. However, this means that because there are instances where connection offers are made but no connection is established, the Distribution Network Operators are unable to recoup all of their costs. Examples of such scenarios are, where developers make speculative requests about developments that do not then go forward, or where a third party connections provider requests an offer on a speculative basis. It is envisaged that without the ability to charge up front, that Distribution Network Operators may pass their assessment and design costs onto all users of the network, rather than those who cause these costs to be incurred.

545.This section will amend the Electricity Act 1989 to allow for up front charging in certain circumstances to allow Distribution Network Operators to recoup the costs of providing network connection offers.

Commentary on Sections

Section 98: Costs connected with making an offer of connection

546.Section 16 of the Electricity Act 1989 states that a Distribution Network Operator is under a duty to make connections to the distribution system in specified circumstances. Section 16A of the Electricity Act 1989 states that when a third party requests a connection from an electricity distributor, the distributor is required to provide a network connection offer. Section 19 of the Electricity Act 1989 enables the electricity distributor to recover costs reasonably incurred in providing a network connection. The provision does not, however, entitle Distribution Network Operators to charge for work carried out, and expenses incurred, for network connection offers where a connection is not subsequently made.

547.Subsection (2) of section 98 addresses this problem by inserting new subsections (4A) to (4C) into section 16A of the Electricity Act 1989.

548.Subsection (4A) of the Electricity Act 1989 provides the Secretary of State with a power to make regulations entitling a Distribution Network Operator to request (to such extent as is reasonable in the circumstances) payment of expenses incurred when making network connection offers under section 16A(5) of the Electricity Act 1989. The power may only be exercised after consultation with the Authority.

549.Subsection (4B) states that the kind of expenses recoverable will be specified in regulations and, consistent with section 19(1) of the Electricity Act 1989, must have been reasonably incurred. The combined effect of subsections (4A) and (4B) is that a Distribution Network Operator may only request payment of his expenses if it is reasonable to do so.

550.Subsection (4C) provides scope for the regulations to specify circumstances under which an electricity distributor is not entitled to require payment and how expenses reasonably incurred are to be calculated.

7

The practice of levying upfront charges was reflected in each DNOs’ Connection Charging Methodology that are approved by the Authority.

Back to top

Options/Help

Print Options

Close

Explanatory Notes

Text created by the government department responsible for the subject matter of the Act to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes were introduced in 1999 and accompany all Public Acts except Appropriation, Consolidated Fund, Finance and Consolidation Acts.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources