The term provision is used to describe a definable element in a piece of legislation that has legislative effect – such as a Part, Chapter or section. A version of a provision is prospective either:
Commencement Orders listed in the ‘Changes to Legislation’ box as not yet applied may bring this prospective version into force.
There are outstanding changes not yet made by the legislation.gov.uk editorial team to Planning Act 2008. Any changes that have already been made by the team appear in the content and are referenced with annotations.![]()
Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.
This section lists the changes and effects yet to be applied to the whole Act, associated Parts and Chapters where applicable. This includes any insertions of whole new Parts, Chapters or provisions yet to be inserted into this Act. These effects are included in this view as they may be (but won’t necessarily be) relevant to the specific provision that you are viewing.
Whole provisions yet to be inserted into this Act (including any effects on those provisions):
This section lists the commencement orders yet to be applied to the whole Act. These effects are included in this view as they may be (but won’t necessarily be) relevant to the specific provision that you are viewing. Where applicable the commencement orders are listed under two headings, firstly those that bring some part of the Act you are viewing into force and secondly, those that bring into force legislation that affects some part of the legislation you are viewing. If you are viewing a prospective version or there is a prospective version available there may be commencement orders listed here that are relevant to the provision you are viewing.
Commencement Orders bringing provisions within this Act into force:
Commencement Orders bringing legislation that affects this Act into force:
(1)When it has decided an application for an order granting development consent, the decision-maker must either—
(a)make an order granting development consent, or
(b)refuse development consent.
(2)The Secretary of State may by regulations make provision regulating the procedure to be followed if the decision-maker proposes to make an order granting development consent on terms which are materially different from those proposed in the application.
Annotations are used to give authority for changes and other effects on the legislation you are viewing and to convey editorial information. They appear at the foot of the relevant provision or under the associated heading. Annotations are categorised by annotation type, such as F-notes for textual amendments and I-notes for commencement information (a full list can be found in the Editorial Practice Guide). Each annotation is identified by a sequential reference number. For F-notes, M-notes and X-notes, the number also appears in bold superscript at the relevant location in the text. All annotations contain links to the affecting legislation.
Commencement Information
Prospective
(1)Development consent may be granted for development which is—
(a)development for which development consent is required, or
(b)associated development.
(2)“Associated development” means development which—
(a)is associated with the development within subsection (1)(a) (or any part of it),
(b)is not the construction or extension of one or more dwellings, and
(c)is within subsection (3) or (4).
(3)Development is within this subsection if it is to be carried out wholly in one or more of the following areas—
(a)England;
(b)waters adjacent to England up to the seaward limits of the territorial sea;
(c)in the case of development in the field of energy, a Renewable Energy Zone, except any part of a Renewable Energy Zone in relation to which the Scottish Ministers have functions.
(4)Development is within this subsection if—
(a)it is to be carried out wholly in Wales,
(b)it is the carrying out or construction of surface works, boreholes or pipes, and
(c)the development within subsection (1)(a) with which it is associated is development within section 17(3).
(5)To the extent that development consent is granted for associated development, section 33 applies to the development as it applies to development for which development consent is required.
(6)In deciding whether development is associated development, a Panel or the Council must have regard to any guidance issued by the Secretary of State.
Prospective
(1)The decision-maker must prepare a statement of its reasons for deciding to—
(a)make an order granting development consent, or
(b)refuse development consent.
(2)The appropriate authority must provide a copy of the statement to each person who is an interested party in relation to the application for the purposes of Chapter 4 (see section 102).
(3)The appropriate authority must publish the statement in such manner as the authority thinks appropriate.
(4)In subsections (2) and (3) “the appropriate authority” means—
(a)the Commission where the decision-maker is a Panel or the Council;
(b)the Secretary of State where the decision-maker is the Secretary of State.
Prospective
(1)This section applies in relation to an order granting development consent.
(2)If the order is made by a Panel or the Council it must be made in the name of the Commission.
(3)Except in a case within subsection (4), the appropriate authority must publish the order in such manner as the authority thinks appropriate.
(4)If the order includes provision made in the exercise of any of the powers conferred by section 120(5)(a) or (b), the order must be contained in a statutory instrument.
(5)If the instrument containing the order is made by a Panel or the Council in the name of the Commission, the Statutory Instruments Act 1946 (c. 36) applies in relation to the instrument as if it had been made by a Minister of the Crown.
(6)As soon as practicable after the instrument is made, the appropriate authority must deposit in the office of the Clerk of the Parliaments a copy of—
(a)the instrument,
(b)the latest version of any plan supplied by the applicant in connection with the application for the order contained in the instrument, and
(c)the statement of reasons prepared under section 116(1).
(7)In this section “the appropriate authority” means—
(a)the Commission where the decision-maker is a Panel or the Council;
(b)the Secretary of State where the decision-maker is the Secretary of State.
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules only you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made):The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Text created by the government department responsible for the subject matter of the Act to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes were introduced in 1999 and accompany all Public Acts except Appropriation, Consolidated Fund, Finance and Consolidation Acts.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: