xmlns:atom="http://www.w3.org/2005/Atom"

SCHEDULES

SCHEDULE 6Acquisition of land shown within limits on deposited plans

Part 2Application of legislation relating to compulsory purchase

Compulsory Purchase Act 1965

3(1)In its application by virtue of paragraph 2, the Compulsory Purchase Act 1965 shall have effect with the following modifications.

(2)Section 4 (time for exercise of powers of compulsory purchase) shall be omitted.

(3)Section 11(1) (power to enter on and take possession of land the subject of a notice to treat after giving not less than 14 days' notice) shall have effect—

(a)in a case where the notice to treat relates only to the acquisition of subsoil or under-surface of land or an easement or other right over land, with the substitution for “fourteen days” of “one month's”, and

(b)in any other case, with the substitution for “fourteen days” of “three months'”.

(4)In section 22(2) (expiry of time limit for exercise of power of compulsory acquisition not to affect acquisition of interests omitted from purchase), for “section 4 of this Act” there shall be substituted “section 6(6) of the Crossrail Act 2008”.

(5)In Schedule 3 (alternative procedures for obtaining right of entry), paragraph 3(3) (requirement as to sureties in relation to bond for compensation) shall be omitted.