SCHEDULE 17Protective provisions

Part 6Protection of Port of London Authority

3The nominated undertaker shall carry out all operations for the construction of any specified work with all reasonable despatch to the reasonable satisfaction of the Port Authority so that navigation in, or the flow or regime of, the river and the exercise of the Port Authority’s statutory functions shall not suffer more interference than is reasonably practicable and the Port Authority shall be entitled by its officer at all reasonable times, on giving such notice as may be reasonable in the circumstances, to inspect and survey such operations.